Cronograma Fisico Financeiro
-
Upload
dinesh-kumar -
Category
Documents
-
view
6 -
download
0
description
Transcript of Cronograma Fisico Financeiro
OBRA: ARENA DA AMAZÔNIA - JANEIRO 2012CRONOGRAMA FÍSICO-FINANCEIRO PARA EMPENHO DO REAJUSTAMENTO
jul-10 ago-10 set-10 out-10 nov-10 dez-10TOTAL 2010
ITEM ATIVIDADE Valor do ITEM 1º MÊS 2º MÊS 3º MÊS 4º MÊS 5º MÊS 6º MÊS
% VALOR % VALOR % VALOR % VALOR % VALOR % VALOR % VALOR
200 1. Mobilização e Desmobilização 1.95% 9,761,208.10 8.87% 866,184.26 4.68% 457,244.26 - - - - 13.56% 1,323,428.52
500 2. Canteiro de Obras 1.10% 5,491,468.79 29.21% 1,604,059.56 16.92% 929,304.96 - - - - 46.13% 2,533,364.52
9089 3. Equipamentos de Apoio 2.78% 13,863,114.06 - - - - - - -
100 4. Administração Local 10.81% 53,982,977.04 2.78% 1,499,527.14 2.78% 1,499,527.14 - - - - 5.56% 2,999,054.28
300 5. Projeto Executivo 3.08% 15,396,690.43 - - - - - - -
9000 6. Serviços Preliminares 2.18% 10,867,110.56 - 9.97% 1,083,108.11 - - - - 9.97% 1,083,108.11
9002 7. Terraplenagem e Pavimentação 1.38% 6,895,008.67 - - - - - - -
9024 8. Fundações Profundas 2.17% 10,831,139.08 - - - - - - -
9090 9. Blocos e Cintas 3.12% 15,589,805.97 - - - - - - -
9067 10. Contenções - Muro de Arrimo 0.16% 806,255.11 - - - - - - -
9003 11. Estrutura de Concreto Armado 17.60% 87,900,320.31 - - - - - - -
1302 12. Estrutura Metálica 23.17% 115,726,020.18 - - - - - - -
3600 13. Equipamentos e Acessorios Esportivos 4.65% 23,204,310.25 - - - - - - -
9015 14. Equipamentos Eletromecânicos 1.34% 6,672,957.20 - - - - - - -
9064 15. Acabamentos Arquitetônicos 4.42% 22,081,551.70 - - - - - - -
9019 16. Paisagismo 0.03% 127,058.85 - - - - - - -
1600 17. Impermeabilizações 1.86% 9,296,974.77 - - - - - - -
9091 18. Sistemas de Ar Condicionados 4.29% 21,432,004.64 - - - - - - -
3200 19. Instalações Eletricas 7.41% 37,021,025.62 - - - - - - -
3400 20. Instalações Hidraulicas/Sanitárias/Gás 1.40% 7,003,321.59 - - - - - - -
9014 21. Instalações de Combate a Incêndios 1.05% 5,228,349.00 - - - - - - -
9010 22. Sistemas Especiais 4.07% 20,330,032.25 - - - - - - -
EXECUÇÃO MENSAL DOS SERVIÇOS 100.00% 499,508,704.17
0.79% 3,969,770.96 0.79% 3,969,184.47 0.00% 0.00% 0.00% 0.00% 1.59% 7,938,955.43
EXECUÇÃO ACUMULADA DOS SERVIÇOS 0.79% 3,969,770.96 1.59% 7,938,955.43 1.59% 7,938,955.43 1.59% 7,938,955.43 1.59% 7,938,955.43 1.59% 7,938,955.43 1.59% 7,938,955.43
CRONOGRAMA DE EMPENHO 5,460,556.65
BNDES MENSAL 80.03% 399,756,877.18
0.00% - 0.00% - - - - - -
BNDES ACUMULADO - - - - - - -
GOV DO ESTADO DO AMAZONAS MENSAL 19.97% 99,751,826.99
100.00% 3,969,770.96 100.00% 3,969,184.47 - - - - 7,938,955.43
GOV DO ESTADO DO AMAZONAS ACUMULADO 3,969,770.96 7,938,955.43 7,938,955.43 7,938,955.43 7,938,955.43 7,938,955.43 7,938,955.43
REAJUSTAMENTO DO CONTRATO 68,102,933.59
- - - - - - -
REAJUSTAMENTO DO CONTRATO ACUMULADO - - - - - - -
Grupo de Serv.
% do ITEM
OBRA: ARENA DA AMAZÔNIA - JANEIRO 2012CRONOGRAMA FÍSICO-FINANCEIRO PARA EMPENHO DO REAJUSTAMENTO
ITEM ATIVIDADE Valor do ITEM
1. Mobilização e Desmobilização 1.95% 9,761,208.10
2. Canteiro de Obras 1.10% 5,491,468.79
3. Equipamentos de Apoio 2.78% 13,863,114.06
4. Administração Local 10.81% 53,982,977.04
5. Projeto Executivo 3.08% 15,396,690.43
6. Serviços Preliminares 2.18% 10,867,110.56
7. Terraplenagem e Pavimentação 1.38% 6,895,008.67
8. Fundações Profundas 2.17% 10,831,139.08
9. Blocos e Cintas 3.12% 15,589,805.97
10. Contenções - Muro de Arrimo 0.16% 806,255.11
11. Estrutura de Concreto Armado 17.60% 87,900,320.31
12. Estrutura Metálica 23.17% 115,726,020.18
13. Equipamentos e Acessorios Esportivos 4.65% 23,204,310.25
14. Equipamentos Eletromecânicos 1.34% 6,672,957.20
15. Acabamentos Arquitetônicos 4.42% 22,081,551.70
16. Paisagismo 0.03% 127,058.85
17. Impermeabilizações 1.86% 9,296,974.77
18. Sistemas de Ar Condicionados 4.29% 21,432,004.64
19. Instalações Eletricas 7.41% 37,021,025.62
20. Instalações Hidraulicas/Sanitárias/Gás 1.40% 7,003,321.59
21. Instalações de Combate a Incêndios 1.05% 5,228,349.00
22. Sistemas Especiais 4.07% 20,330,032.25
EXECUÇÃO MENSAL DOS SERVIÇOS 100.00% 499,508,704.17
EXECUÇÃO ACUMULADA DOS SERVIÇOS
CRONOGRAMA DE EMPENHO
BNDES MENSAL 80.03% 399,756,877.18
BNDES ACUMULADO
GOV DO ESTADO DO AMAZONAS MENSAL 19.97% 99,751,826.99
GOV DO ESTADO DO AMAZONAS ACUMULADO
REAJUSTAMENTO DO CONTRATO 68,102,933.59
REAJUSTAMENTO DO CONTRATO ACUMULADO
% do ITEM
jan-11 fev-11 mar-11 abr-11 mai-11 jun-11 jul-117º MÊS 8º MÊS 9º MÊS 10º MÊS 11º MÊS 12º MÊS 13º MÊS
% VALOR % VALOR % VALOR % VALOR % VALOR % VALOR % VALOR
- - 4.76% 464,952.78 4.76% 464,952.78 - 7.94% 774,921.30 1.59% 154,984.26
- - 25.70% 1,411,420.64 1.74% 95,561.32 - 4.39% 240,864.66 0.87% 47,780.66
- - - - - 1.11% 153,680.81 1.51% 209,660.05
- - 8.33% 4,498,581.42 5.56% 2,999,054.28 2.78% 1,499,527.14 13.89% 7,497,635.70 2.78% 1,499,527.14
- 49.44% 7,611,527.91 - 10.07% 1,550,455.30 38.26% 5,890,424.49 2.24% 344,282.73 -
- - 65.48% 7,115,759.06 4.72% 512,967.39 - 0.36% 38,817.11 0.08% 8,783.54
- - - 19.58% 1,350,075.63 - 1.10% 75,848.41 -
- - 6.55% 709,043.68 19.94% 2,160,143.93 20.29% 2,197,100.51 37.38% 4,048,606.22 -
- - - 0.71% 110,719.16 0.97% 151,413.14 20.91% 3,259,614.84 4.49% 700,105.86
- - - - - - -
- - - 0.07% 63,398.14 0.09% 77,265.25 5.07% 4,458,483.84 0.91% 796,116.99
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
0.00% - 1.52% 7,611,527.91 2.84% 14,199,757.58 1.86% 9,307,327.93 1.97% 9,815,730.53 4.18% 20,892,755.62 0.68% 3,416,958.50
1.59% 7,938,955.43 3.11% 15,550,483.34 5.96% 29,750,240.92 7.82% 39,057,568.85 9.78% 48,873,299.38 13.97% 69,766,055.00 14.65% 73,183,013.50 40,935,275.33 5,963,067.59 12,295,359.74 12,928,141.63 12,419,739.03 (2,554,737.55) 14,921,059.57
40,935,275.33 13,574,595.50 26,495,117.32 22,235,469.56 22,235,469.56 18,338,018.07 18,338,018.07
- 78.8278% 6,000,000.00 98.0000% 13,915,762.43 0.0000% - 58.8098% 5,772,616.00 98.0000% 20,474,900.50 98.0000% 3,348,619.33
- 6,000,000.00 19,915,762.43 19,915,762.43 25,688,378.43 46,163,278.93 49,511,898.26
- 21.1722% 1,611,527.91 2.0000% 283,995.15 100.0000% 9,307,327.93 41.1902% 4,043,114.53 2.0000% 417,855.12 2.0000% 68,339.17
7,938,955.43 9,550,483.34 9,834,478.49 19,141,806.42 23,184,920.95 23,602,776.07 23,671,115.24
- 0.074 563,253.06 0.074 1,050,782.06 0.074 688,742.26 0.074 726,364.05 0.074 1,546,063.91 0.074 252,854.92
- 563,253.06 1,614,035.12 2,302,777.38 3,029,141.43 4,575,205.34 4,828,060.26
OBRA: ARENA DA AMAZÔNIA - JANEIRO 2012CRONOGRAMA FÍSICO-FINANCEIRO PARA EMPENHO DO REAJUSTAMENTO
ITEM ATIVIDADE Valor do ITEM
1. Mobilização e Desmobilização 1.95% 9,761,208.10
2. Canteiro de Obras 1.10% 5,491,468.79
3. Equipamentos de Apoio 2.78% 13,863,114.06
4. Administração Local 10.81% 53,982,977.04
5. Projeto Executivo 3.08% 15,396,690.43
6. Serviços Preliminares 2.18% 10,867,110.56
7. Terraplenagem e Pavimentação 1.38% 6,895,008.67
8. Fundações Profundas 2.17% 10,831,139.08
9. Blocos e Cintas 3.12% 15,589,805.97
10. Contenções - Muro de Arrimo 0.16% 806,255.11
11. Estrutura de Concreto Armado 17.60% 87,900,320.31
12. Estrutura Metálica 23.17% 115,726,020.18
13. Equipamentos e Acessorios Esportivos 4.65% 23,204,310.25
14. Equipamentos Eletromecânicos 1.34% 6,672,957.20
15. Acabamentos Arquitetônicos 4.42% 22,081,551.70
16. Paisagismo 0.03% 127,058.85
17. Impermeabilizações 1.86% 9,296,974.77
18. Sistemas de Ar Condicionados 4.29% 21,432,004.64
19. Instalações Eletricas 7.41% 37,021,025.62
20. Instalações Hidraulicas/Sanitárias/Gás 1.40% 7,003,321.59
21. Instalações de Combate a Incêndios 1.05% 5,228,349.00
22. Sistemas Especiais 4.07% 20,330,032.25
EXECUÇÃO MENSAL DOS SERVIÇOS 100.00% 499,508,704.17
EXECUÇÃO ACUMULADA DOS SERVIÇOS
CRONOGRAMA DE EMPENHO
BNDES MENSAL 80.03% 399,756,877.18
BNDES ACUMULADO
GOV DO ESTADO DO AMAZONAS MENSAL 19.97% 99,751,826.99
GOV DO ESTADO DO AMAZONAS ACUMULADO
REAJUSTAMENTO DO CONTRATO 68,102,933.59
REAJUSTAMENTO DO CONTRATO ACUMULADO
% do ITEM
ago-11 set-11 out-11 nov-11 dez-11TOTAL 2011
jan-1214º MÊS 15º MÊS 16º MÊS 17º MÊS 18º MÊS 19º MÊS
% VALOR % VALOR % VALOR % VALOR % VALOR % VALOR % VALOR
- - 12.60% 1,229,760.10 1.59% 154,984.26 1.59% 154,984.26 34.83% 3,399,539.74 1.59% 154,984.26
- - 1.74% 95,561.32 0.97% 53,067.41 0.93% 51,260.34 36.34% 1,995,516.35 0.97% 53,477.11
- - 4.05% 561,766.06 2.54% 352,106.01 2.54% 352,106.01 11.75% 1,629,318.94 3.76% 520,893.09
- - 5.56% 2,999,054.28 2.78% 1,499,527.14 2.78% 1,499,527.14 44.44% 23,992,434.24 2.78% 1,499,527.14
- - - - - 100.00% 15,396,690.43 -
- - 2.23% 242,573.10 - - 72.87% 7,918,900.20 17.16% 1,865,102.25
- - - - - 20.68% 1,425,924.04 19.14% 1,319,963.79
- - 1.29% 139,432.75 - - 85.44% 9,254,327.09 14.56% 1,576,811.99
- - 24.48% 3,816,203.07 11.49% 1,791,884.27 14.21% 2,215,209.59 77.26% 12,045,149.93 22.74% 3,544,656.04
- - - - - 0.00% - 57.05% 459,953.11
- - 5.30% 4,660,282.56 3.10% 2,725,773.86 4.77% 4,195,061.13 19.31% 16,976,381.77 10.00% 8,790,032.03
- - - - - 0.00% - 25.95% 30,035,627.71
- - - - - - -
- - - - - - -
- - - - - 0.00% - -
- - - - - - -
- - - - - 0.00% - 3.00% 278,909.24
- - - - - - -
- - - - - 0.00% - -
- - - - 0.39% 27,547.28 0.39% 27,547.28 6.00% 420,199.30
- - - - - 0.00% - -
- - - - - - -
0.00% - 0.00% - 2.75% 13,744,633.24 1.32% 6,577,342.95 1.70% 8,495,695.75 18.83% 94,061,730.01 10.11% 50,520,137.06
14.65% 73,183,013.50 14.65% 73,183,013.50 17.40% 86,927,646.74 18.72% 93,504,989.69 20.42% 102,000,685.44 20.42% 102,000,685.44 30.53% 152,520,822.50 35,979,000.19 21,299,646.70 7,555,013.46 14,722,303.75 12,818,743.75 (30,834,988.20)
35,979,000.19 21,299,646.70 21,299,646.70 21,299,646.70 21,314,439.50 19,685,148.86
- - 98.0000% 13,469,740.57 98.0000% 6,445,796.09 98.0000% 8,325,781.83 77,753,216.75 81.0056% 40,924,128.05
49,511,898.26 49,511,898.26 62,981,638.83 69,427,434.92 77,753,216.75 77,753,216.75 118,677,344.80
- - 2.0000% 274,892.67 2.0000% 131,546.86 2.0000% 169,913.92 16,308,513.26 18.9944% 9,596,009.01
23,671,115.24 23,671,115.24 23,946,007.91 24,077,554.77 24,247,468.69 24,247,468.69 33,843,477.70
0.074 - 0.074 - 0.074 1,017,102.85 0.074 486,723.37 0.074 628,681.48 6,960,567.96 0.074 3,759,774.27
4,828,060.26 4,828,060.26 5,845,163.11 6,331,886.48 6,960,567.96 6,960,567.96 10,720,342.23
OBRA: ARENA DA AMAZÔNIA - JANEIRO 2012CRONOGRAMA FÍSICO-FINANCEIRO PARA EMPENHO DO REAJUSTAMENTO
ITEM ATIVIDADE Valor do ITEM
1. Mobilização e Desmobilização 1.95% 9,761,208.10
2. Canteiro de Obras 1.10% 5,491,468.79
3. Equipamentos de Apoio 2.78% 13,863,114.06
4. Administração Local 10.81% 53,982,977.04
5. Projeto Executivo 3.08% 15,396,690.43
6. Serviços Preliminares 2.18% 10,867,110.56
7. Terraplenagem e Pavimentação 1.38% 6,895,008.67
8. Fundações Profundas 2.17% 10,831,139.08
9. Blocos e Cintas 3.12% 15,589,805.97
10. Contenções - Muro de Arrimo 0.16% 806,255.11
11. Estrutura de Concreto Armado 17.60% 87,900,320.31
12. Estrutura Metálica 23.17% 115,726,020.18
13. Equipamentos e Acessorios Esportivos 4.65% 23,204,310.25
14. Equipamentos Eletromecânicos 1.34% 6,672,957.20
15. Acabamentos Arquitetônicos 4.42% 22,081,551.70
16. Paisagismo 0.03% 127,058.85
17. Impermeabilizações 1.86% 9,296,974.77
18. Sistemas de Ar Condicionados 4.29% 21,432,004.64
19. Instalações Eletricas 7.41% 37,021,025.62
20. Instalações Hidraulicas/Sanitárias/Gás 1.40% 7,003,321.59
21. Instalações de Combate a Incêndios 1.05% 5,228,349.00
22. Sistemas Especiais 4.07% 20,330,032.25
EXECUÇÃO MENSAL DOS SERVIÇOS 100.00% 499,508,704.17
EXECUÇÃO ACUMULADA DOS SERVIÇOS
CRONOGRAMA DE EMPENHO
BNDES MENSAL 80.03% 399,756,877.18
BNDES ACUMULADO
GOV DO ESTADO DO AMAZONAS MENSAL 19.97% 99,751,826.99
GOV DO ESTADO DO AMAZONAS ACUMULADO
REAJUSTAMENTO DO CONTRATO 68,102,933.59
REAJUSTAMENTO DO CONTRATO ACUMULADO
% do ITEM
fev-12 mar-12 abr-12 mai-12 jun-12 jul-12 ago-1220º MÊS 21º MÊS 22º MÊS 23º MÊS 24º MÊS 25º MÊS 26º MÊS
% VALOR % VALOR % VALOR % VALOR % VALOR % VALOR % VALOR
1.59% 154,984.26 1.59% 154,984.26 1.59% 154,984.26 1.59% 154,984.26 1.59% 154,984.26 1.59% 154,984.26 1.59% 154,984.26
0.97% 53,477.11 0.97% 53,477.11 0.97% 53,477.11 0.97% 53,477.11 0.97% 53,477.11 0.97% 53,477.11 0.97% 53,477.11
6.30% 872,999.10 6.30% 872,999.10 7.75% 1,074,490.92 7.94% 1,100,598.14 6.16% 853,700.52 6.45% 894,352.93 6.74% 935,005.34
2.78% 1,499,527.14 2.78% 1,499,527.14 2.78% 1,499,527.14 2.78% 1,499,527.14 2.78% 1,499,527.14 2.78% 1,499,527.14 2.78% 1,499,527.14
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
7.76% 62,543.59 7.67% 61,804.53 20.56% 165,763.66 6.97% 56,190.22 - - -
9.00% 7,911,028.83 9.00% 7,911,028.83 8.00% 7,032,025.62 8.00% 7,032,025.62 7.00% 6,153,022.42 7.00% 6,153,022.42 6.00% 5,274,019.22
9.50% 10,993,971.92 9.00% 10,415,341.82 9.00% 10,415,341.82 4.24% 4,904,854.46 5.06% 5,859,304.84 4.06% 4,702,044.64 4.06% 4,702,044.64
- - - - - - -
- - - - - - -
9.42% 2,078,983.75 10.09% 2,228,571.40 12.47% 2,753,232.15 6.10% 1,346,738.68 7.17% 1,584,306.07 7.77% 1,715,818.33 8.30% 1,832,979.63
- - - - - - -
8.00% 743,757.98 8.00% 743,757.98 20.00% 1,859,394.95 15.00% 1,394,546.22 10.00% 929,697.48 10.00% 929,697.48 6.00% 557,818.49
- - - 10.72% 2,297,675.29 10.72% 2,297,675.29 11.49% 2,462,736.22 11.75% 2,517,910.87
- - - 10.72% 3,968,937.90 10.72% 3,968,937.90 11.49% 4,254,059.40 11.75% 4,349,366.50
6.00% 420,199.30 6.00% 420,199.30 6.00% 420,199.30 6.00% 420,199.30 7.44% 521,154.56 8.49% 594,646.99 8.75% 612,676.38
- - - 10.72% 560,519.11 10.72% 560,519.11 11.49% 600,785.82 11.75% 614,245.70
- - - 10.72% 2,179,535.39 10.72% 2,179,535.39 11.49% 2,336,109.37 11.75% 2,388,447.10
4.96% 24,791,472.98 4.88% 24,361,691.47 5.09% 25,428,436.93 5.40% 26,969,808.84 5.33% 26,615,842.09 5.28% 26,351,262.11 5.10% 25,492,502.38
35.50% 177,312,295.48 40.37% 201,673,986.95 45.47% 227,102,423.88 50.86% 254,072,232.72 56.19% 280,688,074.81 61.47% 307,039,336.92 66.57% 332,531,839.30 (5,106,324.12) (3,337,042.32) (18,393,091.16) (19,934,463.07) (18,017,116.84) (17,752,536.86) (16,882,227.48)
19,685,148.86 21,024,649.15 7,035,345.77 7,035,345.77 8,598,725.25 8,598,725.25 8,610,274.90
81.0056% 20,082,475.50 81.0056% 19,734,328.51 81.0056% 20,598,451.82 81.0056% 21,847,049.01 81.0056% 21,560,316.21 81.0056% 21,345,991.67 81.0056% 20,650,348.40
138,759,820.30 158,494,148.81 179,092,600.63 200,939,649.64 222,499,965.85 243,845,957.52 264,496,305.92
18.9944% 4,708,997.48 18.9944% 4,627,362.96 18.9944% 4,829,985.11 18.9944% 5,122,759.83 18.9944% 5,055,525.88 18.9944% 5,005,270.44 18.9944% 4,842,153.98
38,552,475.18 43,179,838.14 48,009,823.25 53,132,583.08 58,188,108.96 63,193,379.40 68,035,533.38
0.153 3,803,540.01 0.153 3,737,602.37 0.153 3,901,263.85 0.153 4,137,743.13 0.153 4,083,437.09 0.153 4,042,844.88 0.153 3,911,092.85
14,523,882.24 18,261,484.61 22,162,748.46 26,300,491.59 30,383,928.68 34,426,773.56 38,337,866.41
OBRA: ARENA DA AMAZÔNIA - JANEIRO 2012CRONOGRAMA FÍSICO-FINANCEIRO PARA EMPENHO DO REAJUSTAMENTO
ITEM ATIVIDADE Valor do ITEM
1. Mobilização e Desmobilização 1.95% 9,761,208.10
2. Canteiro de Obras 1.10% 5,491,468.79
3. Equipamentos de Apoio 2.78% 13,863,114.06
4. Administração Local 10.81% 53,982,977.04
5. Projeto Executivo 3.08% 15,396,690.43
6. Serviços Preliminares 2.18% 10,867,110.56
7. Terraplenagem e Pavimentação 1.38% 6,895,008.67
8. Fundações Profundas 2.17% 10,831,139.08
9. Blocos e Cintas 3.12% 15,589,805.97
10. Contenções - Muro de Arrimo 0.16% 806,255.11
11. Estrutura de Concreto Armado 17.60% 87,900,320.31
12. Estrutura Metálica 23.17% 115,726,020.18
13. Equipamentos e Acessorios Esportivos 4.65% 23,204,310.25
14. Equipamentos Eletromecânicos 1.34% 6,672,957.20
15. Acabamentos Arquitetônicos 4.42% 22,081,551.70
16. Paisagismo 0.03% 127,058.85
17. Impermeabilizações 1.86% 9,296,974.77
18. Sistemas de Ar Condicionados 4.29% 21,432,004.64
19. Instalações Eletricas 7.41% 37,021,025.62
20. Instalações Hidraulicas/Sanitárias/Gás 1.40% 7,003,321.59
21. Instalações de Combate a Incêndios 1.05% 5,228,349.00
22. Sistemas Especiais 4.07% 20,330,032.25
EXECUÇÃO MENSAL DOS SERVIÇOS 100.00% 499,508,704.17
EXECUÇÃO ACUMULADA DOS SERVIÇOS
CRONOGRAMA DE EMPENHO
BNDES MENSAL 80.03% 399,756,877.18
BNDES ACUMULADO
GOV DO ESTADO DO AMAZONAS MENSAL 19.97% 99,751,826.99
GOV DO ESTADO DO AMAZONAS ACUMULADO
REAJUSTAMENTO DO CONTRATO 68,102,933.59
REAJUSTAMENTO DO CONTRATO ACUMULADO
% do ITEM
set-12 out-12 nov-12 dez-12TOTAL 2012
jan-13 fev-1327º MÊS 28º MÊS 29º MÊS 30º MÊS 31º MÊS 32º MÊS
% VALOR % VALOR % VALOR % VALOR % VALOR % VALOR % VALOR
1.59% 154,984.26 1.59% 154,984.26 1.59% 154,984.26 1.59% 154,984.26 19.05% 1,859,811.12 1.59% 154,984.26 1.59% 154,984.26
0.97% 53,477.11 0.97% 53,477.11 0.97% 53,477.11 0.97% 53,477.11 11.69% 641,725.32 0.97% 53,477.11 0.97% 53,477.11
18.10% 2,509,887.62 6.74% 935,005.34 6.45% 894,352.93 5.55% 769,510.09 88.25% 12,233,795.12 - -
2.78% 1,499,527.14 2.78% 1,499,527.14 2.78% 1,499,527.14 2.78% 1,499,527.14 33.33% 17,994,325.68 2.78% 1,499,527.14 2.78% 1,499,527.14
- - - - 0.00% - - -
- - - - 17.16% 1,865,102.25 - -
4.00% 275,800.35 5.00% 344,750.43 5.24% 361,192.41 6.08% 419,043.79 39.46% 2,720,750.77 14.76% 1,017,418.82 7.35% 506,947.58
- - - - 14.56% 1,576,811.99 - -
- - - - 22.74% 3,544,656.04 - -
- - - - 100.00% 806,255.11 - -
5.00% 4,395,016.02 5.00% 4,395,016.02 4.00% 3,516,012.81 2.69% 2,361,688.70 80.69% 70,923,938.54 - -
5.90% 6,829,088.89 4.06% 4,702,044.64 4.06% 4,702,044.64 4.06% 4,702,044.64 88.97% 102,963,754.66 3.68% 4,254,088.51 1.84% 2,127,044.25
- 5.00% 1,160,215.51 11.31% 2,625,244.86 25.00% 5,801,077.56 41.31% 9,586,537.93 - -
- - - - 0.00% - - 21.67% 1,445,807.39
7.08% 1,563,912.15 6.56% 1,449,015.40 5.74% 1,267,266.88 5.72% 1,262,792.09 86.42% 19,083,616.53 3.05% 673,919.87 3.73% 822,681.71
- - - - 0.00% - - -
5.00% 464,848.74 5.00% 464,848.74 5.00% 464,848.74 5.00% 464,848.73 100.00% 9,296,974.77 - -
11.93% 2,556,531.99 11.27% 2,414,927.66 10.82% 2,319,249.07 10.38% 2,223,570.48 89.07% 19,090,276.87 1.31% 280,080.82 2.45% 524,668.36
11.93% 4,416,079.49 11.27% 4,171,476.27 10.82% 4,006,203.84 10.38% 3,840,931.43 89.07% 32,975,992.73 1.31% 483,803.52 2.45% 906,296.96
8.93% 625,296.57 8.27% 579,024.62 8.82% 617,793.01 8.38% 586,528.18 89.07% 6,238,116.81 1.31% 91,521.82 2.45% 171,445.52
11.93% 623,667.35 11.27% 589,122.90 10.82% 565,782.05 10.38% 542,441.22 89.07% 4,657,083.26 1.31% 68,325.87 2.45% 127,993.13
11.93% 2,425,082.42 11.27% 2,290,758.99 10.82% 2,199,999.92 10.37% 2,109,240.83 89.07% 18,108,709.41 1.31% 265,679.87 2.45% 497,691.41
5.68% 28,393,200.10 5.05% 25,204,195.03 5.05% 25,247,979.67 5.36% 26,791,706.25 67.30% 336,168,234.91 1.77% 8,842,827.61 1.77% 8,838,564.82
72.26% 360,925,039.40 77.30% 386,129,234.43 82.36% 411,377,214.10 87.72% 438,168,920.35 87.72% 438,168,920.35 89.49% 447,011,747.96 91.26% 455,850,312.78 (19,782,925.20) (16,593,920.13) (12,771,866.68) (14,315,593.26) 3,633,285.38 3,637,548.17
8,610,274.90 8,610,274.90 12,476,112.99 12,476,112.99 12,476,112.99 12,476,112.99
81.0056% 23,000,075.30 81.0056% 20,416,803.37 81.0056% 20,452,271.37 81.0056% 21,702,775.98 272,315,015.19 81.0056% 7,163,183.44 81.0056% 7,159,730.35
287,496,381.22 307,913,184.59 328,365,455.96 350,068,231.94 350,068,231.94 357,231,415.38 364,391,145.73
18.9944% 5,393,124.80 18.9944% 4,787,391.66 18.9944% 4,795,708.30 18.9944% 5,088,930.27 63,853,219.72 18.9944% 1,679,644.17 18.9944% 1,678,834.47
73,428,658.18 78,216,049.84 83,011,758.14 88,100,688.41 88,100,688.41 89,780,332.58 91,459,167.05
0.153 4,356,121.67 0.153 3,866,860.36 0.153 3,873,577.86 0.153 4,110,418.40 47,584,276.74 0.153 1,356,678.10 0.232 2,054,270.72
42,693,988.08 46,560,848.44 50,434,426.30 54,544,844.70 54,544,844.70 55,901,522.80 57,955,793.52
OBRA: ARENA DA AMAZÔNIA - JANEIRO 2012CRONOGRAMA FÍSICO-FINANCEIRO PARA EMPENHO DO REAJUSTAMENTO
ITEM ATIVIDADE Valor do ITEM
1. Mobilização e Desmobilização 1.95% 9,761,208.10
2. Canteiro de Obras 1.10% 5,491,468.79
3. Equipamentos de Apoio 2.78% 13,863,114.06
4. Administração Local 10.81% 53,982,977.04
5. Projeto Executivo 3.08% 15,396,690.43
6. Serviços Preliminares 2.18% 10,867,110.56
7. Terraplenagem e Pavimentação 1.38% 6,895,008.67
8. Fundações Profundas 2.17% 10,831,139.08
9. Blocos e Cintas 3.12% 15,589,805.97
10. Contenções - Muro de Arrimo 0.16% 806,255.11
11. Estrutura de Concreto Armado 17.60% 87,900,320.31
12. Estrutura Metálica 23.17% 115,726,020.18
13. Equipamentos e Acessorios Esportivos 4.65% 23,204,310.25
14. Equipamentos Eletromecânicos 1.34% 6,672,957.20
15. Acabamentos Arquitetônicos 4.42% 22,081,551.70
16. Paisagismo 0.03% 127,058.85
17. Impermeabilizações 1.86% 9,296,974.77
18. Sistemas de Ar Condicionados 4.29% 21,432,004.64
19. Instalações Eletricas 7.41% 37,021,025.62
20. Instalações Hidraulicas/Sanitárias/Gás 1.40% 7,003,321.59
21. Instalações de Combate a Incêndios 1.05% 5,228,349.00
22. Sistemas Especiais 4.07% 20,330,032.25
EXECUÇÃO MENSAL DOS SERVIÇOS 100.00% 499,508,704.17
EXECUÇÃO ACUMULADA DOS SERVIÇOS
CRONOGRAMA DE EMPENHO
BNDES MENSAL 80.03% 399,756,877.18
BNDES ACUMULADO
GOV DO ESTADO DO AMAZONAS MENSAL 19.97% 99,751,826.99
GOV DO ESTADO DO AMAZONAS ACUMULADO
REAJUSTAMENTO DO CONTRATO 68,102,933.59
REAJUSTAMENTO DO CONTRATO ACUMULADO
% do ITEM
mar-13 abr-13 mai-13 jun-13TOTAL 2013
33º MÊS 34º MÊS 35º MÊS 36º MÊS% VALOR % VALOR % VALOR % VALOR % VALOR
1.59% 154,984.26 9.27% 904,491.98 9.27% 904,491.98 9.27% 904,491.98 32.56% 3,178,428.72
0.97% 53,477.11 0.97% 53,477.11 0.97% 53,477.11 0.97% 53,477.05 5.84% 320,862.60
- - - - 0.00% -
2.78% 1,499,527.14 2.78% 1,499,527.14 2.78% 1,499,527.14 2.78% 1,499,527.14 16.67% 8,997,162.84
- - - - 0.00% -
- - - - 0.00% -
9.99% 688,641.02 6.10% 420,356.69 1.67% 114,969.75 - 39.86% 2,748,333.86
- - - - 0.00% -
- - - - 0.00% -
- - - - 0.00% -
- - - - 0.00% -
1.84% 2,127,044.25 1.84% 2,127,044.25 1.84% 2,127,044.26 - 11.03% 12,762,265.52
21.44% 4,975,328.78 24.36% 5,651,763.14 9.43% 2,189,225.38 3.45% 801,455.02 58.69% 13,617,772.32
35.00% 2,335,535.02 36.67% 2,446,750.97 6.67% 444,863.82 - 100.00% 6,672,957.20
3.81% 840,306.44 2.44% 538,718.97 0.55% 122,308.18 - 13.58% 2,997,935.17
34.73% 44,131.56 50.00% 63,529.43 15.27% 19,397.86 - 100.00% 127,058.85
- - - - 0.00% -
2.89% 620,346.95 1.47% 314,623.10 1.47% 314,623.10 1.34% 287,385.44 10.93% 2,341,727.77
2.89% 1,071,569.39 1.47% 543,470.85 1.47% 543,470.85 1.34% 496,421.32 10.93% 4,045,032.89
2.89% 202,710.35 1.47% 102,809.18 1.07% 75,261.90 1.34% 93,908.73 10.53% 737,657.50
2.89% 151,333.97 1.47% 76,752.47 1.47% 76,752.47 1.34% 70,107.83 10.93% 571,265.74
2.89% 588,450.48 1.47% 298,446.08 1.47% 298,446.08 1.34% 272,608.92 10.93% 2,221,322.84
3.07% 15,353,386.72 3.01% 15,041,761.36 1.76% 8,783,859.88 0.90% 4,479,383.43 12.28% 61,339,783.82
94.33% 471,203,699.50 97.34% 486,245,460.86 99.10% 495,029,320.74 100.00% 499,508,704.17 100.00% 499,508,704.17 (2,877,273.73) (2,556,366.65) (144,417.93) 2,746,706.89
12,476,112.99 12,485,394.71 8,639,441.95 7,226,090.32
81.0056% 12,437,099.36 81.0056% 12,184,665.44 81.0056% 7,115,416.30 81.0056% 3,628,550.35 49,688,645.24
376,828,245.09 389,012,910.53 396,128,326.83 399,756,877.18 399,756,877.18
18.9944% 2,916,287.36 18.9944% 2,857,095.92 18.9944% 1,668,443.58 18.9944% 850,833.08 11,651,138.58
94,375,454.41 97,232,550.33 98,900,993.91 99,751,826.99 99,751,826.99
0.232 3,568,454.10 0.232 3,496,025.72 0.232 2,041,556.13 0.232 1,041,104.12 13,558,088.89
61,524,247.62 65,020,273.34 67,061,829.47 68,102,933.59 68,102,933.59