Pne Rb 57 Rio Blanco

download Pne Rb 57 Rio Blanco

of 98

Transcript of Pne Rb 57 Rio Blanco

  • 8/7/2019 Pne Rb 57 Rio Blanco

    1/98

    N V O - 1 4 5

    ProjectRio Blanco

    DEFINITION PLANALTERNATE REENTRYAND TESTING

    MAY 1974

    U.S. ATOMIC ENERGY COMMISSIONCONTINENTAL OIL COMPANY

    DISTRIBUTION C ;T IS UNUMITEU

  • 8/7/2019 Pne Rb 57 Rio Blanco

    2/98

    DISCLAIMER

    This report was prepared as an account of work sponsored by anagency of the United States Government. Neither the United StatesGovernment nor any agency Thereof, nor any of their employees,makes any warranty, express or implied, or assumes any legalliability or responsibility for the accuracy, completeness, orusefulness of any information, apparatus, product, or processdisclosed, or represents that its use would not infringe privatelyowned rights. Reference herein to any specific commercial product,process, or service by trade name, trademark, manufacturer, orotherwise does not necessarily constitute or imply its endorsement,recommendation, or favoring by the United States Government or anyagency thereof. The views and opinions of authors expressed hereindo not necessarily state or reflect those of the United StatesGovernment or any agency thereof.

  • 8/7/2019 Pne Rb 57 Rio Blanco

    3/98

    DISCLAIMER

    Portions of this document may be illegible inelectronic image products. Images are producedfrom the best available original document.

  • 8/7/2019 Pne Rb 57 Rio Blanco

    4/98

    PROJECT RIO BLANCO-ALTERNATE REENTRY-RB-AR-2 l''^ ^ ^^REVISED SCHEDULE OF MAJOR ACTIVITIES

    EXPECTED STARTING S COMPLETION DATESO P E R A T I O N

    D SAFE MOBILIZATIONILL TO 2 20 0'

    1. TO KOP

    DWC a OTIS5" LINER

    DOWNOW TEST

    Roi 1 UP a

    MAY24

    JUNE!34 171

    L,1L

    JULY1 14

    L L -

    IT E M ^ e IS THE CRITICALPATH. SUBSEQUENT OPER-AIIONS Wll 1 SLIP PKOPOK-TIONALLY AS ^'e SLIPS.

    AUG SEPT! 15 26

    L.WMtWM^J

    OCT21

    u .f i i

    N

    1

    a na

    Con

    REVISED' AUGUST 13. 1974

  • 8/7/2019 Pne Rb 57 Rio Blanco

    5/98

    PROJECT RIO BLANCO-ALTERNATE REENTRY-RB-AR-2REVISED SCHEDULE OF MAJOR ACTIVITIES

    O P E R A T I O NE PREPARATION

    G UPD SAFE MOBILIZATIONILL TO 2 20 0'

    KOPPT aNG.NIPPLE UPDWC a OTIS

    5" LINERRIG DOWNOW TEST

    EXPECTED STARTING a COMPLETION DATESMAY

    24L JUNE!34 171

    te

    JULY1 14

    L.LITEM^e IS THE CRITICALPATH. SUBSEQUENT OPERATIONS WILL SLIP PROPORTIONALLY AS ^ 6 SLIPS.

    AUG 1 SEPT! 1.5 26

    s

    JBMMBKi

    OCT 121 1

    1 1 1 1

    N

    1

    a

    s s & r z 1Con

    REVISED' AUGUST 13. 1974

  • 8/7/2019 Pne Rb 57 Rio Blanco

    6/98

    TABLE OF CONTENTS

    PAGETABLE OF CONTENTS iTABLE OF FIGURES AND TABLES iiiI. INTRODUCTION 1

    A. Background 1B. Program Objectives , 3

    II. GENERALIZED SITE ACTIVITIES 6A. Site Preparation 6B. Power Installation 6C. Conmunicatlons 6D. Vehicles 7E . G e n e r a l O p e r a t i o n a l a nd L o g i s t i c a l S u p p o r t 7F. Occupational Health and Safety 7

    III. REENTRY OPERATIONS 9A. Drilling Operations 9

    IV. PRODUCTION TESTING 28A. General 28B. Site Layout 28C. Equipment 28D. Test Schedule 33E. Automation and Alarm Systems 33F. Water Disposal 37G. Recompletion and Testing of Fort Union Sands 37

    V, RADIOLOGICAL SAFETY AND ENVIRONMENTAL SAMPLING 39A. Purpose 39B . Scope 39C. Criteria 40D. R e s p o n s i b i l i t y 4 0E. Operational Requirements 41F. Environmental Sampling Program 59

    VI. SITE ROLL-UP 62A. Documentation 62B. Equipment Removal 62C. Decontamination 62VII. PROGRAM MANAGEMENT 63A. Planning and Administration 63B. Field Operations 64

    - N O T I C E -This report was prepared as an account of worksponsored by the United States Government. Neitherthe United States nor the United Stales Atomic EnergyCommission, nor any of their employees, nor any oftheir contractors, subcontractors, or their employees,makes any warranty, express or implied, or assumes anylegal liability or responsibility for the accuracy, completeness or usefulness of any information, apparatus,product or process disclosed, or represents that its usewould not infringe privately owned rights.j i - ' i o :

  • 8/7/2019 Pne Rb 57 Rio Blanco

    7/98

    TABLE OF CONTENTS (cont.)

    PAGEVIII. TECHNICAL DOCUMENTATION AND REPORTING 66A. General 66B. Basic Principles 66C. Proprietary Information 67D. Review and Processing of Formal Reports,Symposia Presentations, and InformationalRelease to the Public 67

    IX. SECURITY PROCEDURES 72A. General 72B. Classified Material 73X. PUBLIC AFFAIRS 74

    A. General 74B. Briefings and Meetings 74XI. SCHEDULING 76

    XII. COST ESTIMATES 78A. Drilling 78B. Production TestingPhase I 79C. Production TestingPhase II 80D. Site Cleanup 81E. Environmental Sampling 81

    APPENDIX A 82Part 1 82Part 2 88APPENDIX B 89APPENDIX C 90

    ii

  • 8/7/2019 Pne Rb 57 Rio Blanco

    8/98

    TABLE OF CONTENTS (cont.)

    TABLE OF FIGURES

    FIGURE PAGEI-A-1 AREA MAP PICEANCE BASIN ALTERNATE REENTRY PLAN 2I-A-2 LOCATION MAP 4I-A-3 RB-AR-2 DIRECTIONAL CONFIGURATION 5III-A-1 RB-AR-2 WELLHEAD STATUS 20III-A-2 BLOWOUT PREVENTOR STACK~RB-AR-2 21III-A-3 CONOCOU.S. AEC PROPOSED WELL LOCATION LAYOUT FORDRILLING & COMPLETION OF WELL RB-AR-2 22IV-B-1 PROJECT RIO BLANCO PRODUCTION TEST SYSTEM 29IV-B-2 PROJECT RIO BLANCO LIQUID STORAGE & DISPOSALSYSTEMS 30IV-C-1 RB-AR-2 WELLHEAD & LUBRICATOR FOR PRODUCTION

    TESTING 31IV-E-1 SCHEMATIC OF THE SHUTDOWN & ALARM SYSTEM 36X-1 SCHEDULE OF MAJOR ACTIVITIES 77

    TABLE OF TABLESTABLE

    III-A-1 CEMENT SYSTEMS AND VOLUMES REQUIRED 11III-A-2 CEMENT PROGRAM FOR 7-INCH CASING 17IV-E-1 OUTLINE OF ALARM AND CONTROL FUNCTIONS 34

    iii

  • 8/7/2019 Pne Rb 57 Rio Blanco

    9/98

    I. INTRODUCTION

    A. BackgroundProject Rio Blanco was the first phase of a proposed multiphaseprogram to determine the commercial development potential of a low-permeability natural gas field fractured by nuclear explosives. TheRB-E-01 well is located in the Piceance Basin, Rio Blanco County,Colorado (see Figure I-A-1), and intersects gas-bearing, sandy shalesections too impermeable to produce gas by conventional methods.Three 30-kt nuclear explosives suspended in the emplacement wellat depths below ground level of 5,838, 6,230, and 6,689 feet,respectively, were all detonated simultaneously on May 17, 1973,in an attempt to fracture a vertical section approximately 1,300feet high. The extent of fracturing in this section was expectedto be several hundred feet in diameter.Reentry drilling through the emplacement casing began nearly fourmonths after the detonation, to allow short-lived radionuclidesto decay. Crushed or displaced casing near the chimney necessitatedwhipstock drilling outside of, but parallel to, the emplacementwell in order to connect with the fracture zone. Drilling was completed on October 12, 1973.Following earlier calibration tests, drawdown testing began onNovember 14, and continued until November 20. Information from thistest indicated that production characteristics were below expectations. A different rare gas tracer was emplaced with each explosivefor the purpose of Identifying gas from their respective zones.Only the top tracer was observed. Thus, it appeared that interconnection of the top chimney with the lower regions had not beenaccomplished.High temperatures created some mechanical difficulties that requiredcorrection before extended flow testing could be continued. Theoperation of necessity went into standby status while equipmentunderwent modification. Testing was resumed on January 28, 1974, andcontinued until February 15, at which time the well was shut in. Atotal of 98 million cubic feet of dry chimney gas had been produced during both phases of testing.The January-February phase of testing confirmed early indicationsthat: (1) the chimneys do not appear to be connected, and (2) thestimulated reservoir, in communication with the top chimney, forunknown reasons, has a much lower flow capacity than expected. Inorder to completely evaluate the stimulation effects of the detonation and the reservoir, additional data are required. For this reason, an alternate reentry hole (RB-AR-2) will be drilled into themiddle chimney on an angle from the Fawn Creek Government Number 1

    1

  • 8/7/2019 Pne Rb 57 Rio Blanco

    10/98

    Rangely

    s S *

    R B - A R - 2

    A V ^.lP

    Meeker

    ^ >" ^ A

  • 8/7/2019 Pne Rb 57 Rio Blanco

    11/98

    Well pad about 1,200 feet to the southwest (see Figures I-A-2and I-A-3). Participating in this effort will be the ContinentalOil Company (CONOCO), the U.S. Atomic Energy Commissipn__(^i;Ci..,the Lawrence Livermore Labor"atory (LLL) , the Equity Oil Company(Equity), EG&G, Inc., (EG&G), and CER Geonuclear Corporation(CER).. Program Objectives

    This Project Definition modifies the reentry program described in__ Project Rio Blanco Definition Plan, Vol. III. Reentry-Related DetailedTasks, January, 1973 (PDF Vol. Ill ), and will describe the drilling,production testing, formation sampling safety, security, and environmental programs, as well as the project management aspects of thealternate reentry project. The Plan is, however, subject to modification as dictated by circumstances encountered during the fieldactivity.Drilling will be accomplished in two phases. The first phase willbe the drilling and casing of a 2,200-foot vertical hole. Thesecond phase will extend the hole to approximately 4,700 feetwhere it will be directionally drilled toward the detonation pointof the middle chimney in RB-E-01. The hole will intersect thechimney at about 60 from the vertical, and be used for drawdowntesting and the gathering of data that should define chimneycharacteristics. Subsequently, a second drawdown test will beconducted in the same hole in Ft. Union sands outside of thefracture region created by the uppermost explosion. These datawill assist scientists and engineers in interpreting detonation-related phenomena with respect to low productivity observed duringthe drawdown testing of the upper chimney.The major technical objectives of this program are several: (1)to evaluate the stimulation of the tight gas sands in connectionwith the second nuclear chimney and possibly the bottom chimney;(2) determine the chimney, fracture, and formation characteristicsfrom flow test and pressure buildup data; (3) investigate theradial extent of fracturing while drilling; (4) investigate thechemistry and radiochemistry of the produced gas; (5) determinedetonation-related geometry of the middle chimney such as chimneyand cavity radius; any mineralogical changes in the rock properties; fracture distribution as deduced from studies of micro- andmacrofractures; distribution of melt and the HTO content of meltsamples if economically and technically feasible; (this information will be determined from drilling, logging, and possibly coresampling. The acquisition of this information will depend on thedrilling and hole condition encountered while drilling); and (6)determine the flow capacity (kh) of the Ft. Union zones oppositethe top chimney, but far enough away from the detonation pointthat the flow capacity should not have been altered from thedetonation.

    3

    **

  • 8/7/2019 Pne Rb 57 Rio Blanco

    12/98

    SW 1/4 NW 1 /4, SECTION 14T 3 S , R 9 8 W , 6 T H P .M .

    TO FLARE STACK JlDQUlia-4/

    RB-AR-2, WELL LCXATIONELEV. 6622 .5-S 13''41'V\/141.5FAV N CREEK GOV'T #1 V ELL

    II I!

    V// /(4/ /

    .J/ / o IiII

    I!

    < t / / W|

    ///

    //SJ / / 7R B - E - 0 1EMPLACEMENT WELL

    7

  • 8/7/2019 Pne Rb 57 Rio Blanco

    13/98

    FAWN CREEKG O V ' T N O . I WELL RB -AR-2 WELL

    150'

    2200 '

    HORIZ. SCALE!l"= 400' I

    R B - E - 0 1 W E L Lc; CASING10-^ " CASING

    7" CASING-m K.O. PT.

    5" FJ. LINER

    TD 7893'

    1000'

    2 0 0 0 '

    -3000'

    4 0 0 0 '

    5 0 0 0 '

    6 0 0 0 '

    7 0 0 0 '

    F I G . I - A - 3 R B - A R - 2 D I R E C T IO N A L C O N F I G U R A T I O N5

  • 8/7/2019 Pne Rb 57 Rio Blanco

    14/98

    II. GENERALIZED SITE ACTIVITIES

    Site PreparationDrilling will take place on the Fawn Creek Government Number 1Well pad approximately 1,200 feet southwest of RB-E-01. The FawnCreek pad is level but will be further dressed as necessary toaccommodate reentry activities.1. Trailers

    Trailers will be provided for the LLL/AEC and CONOCO. Theradiological protection trailers will be government furnishedthrough the Radiological Support Contractor, Eberline Instrument Corporation (EIC), under contract to CER, and maintainedon the RB-E-01 pad with the exception of the EIC access control trailer which will be located on the north end of theRB-AR-2 pad. CONOCO, through its contractor, CER, will furnishits monitoring system for radiological effluent documentation(i.e., TRY-KRY System) installed in a trailer on the RB-E-01pad. Personnel trailers will remain at the RB-E-01 pad. AnLLL transportainer will also be located on the RB-AR-2 padwithin the surrounding fence. This transportainer will becapable of locked, temporary storage of any classified materialbrought out of the RB-AR-2 Well during drilling.

    2. FencingThe flare stack is located in the clearing to the northwestand above the RB-E-01 pad. The area, including the flarestack, storage and condensate tanks, separator, and wellheadequipment is fenced with two-strand barbed wire to preventlivestock from entering the area.

    Power InstallationThe White River Electric Company has a power line to the RB-E-01site. Reynolds Electric and Engineering Co., Inc. (REECo) willcontract with the power company to extend the power line to theRB-AR-2 site.CommunicationsTelephone and radio communications will be available at the RB-AR-2project.1. Telephones

    The telephone system to be used will be the CER microwave systemidentified in detail in Project Rio Blanco Definition Plan,

    6

  • 8/7/2019 Pne Rb 57 Rio Blanco

    15/98

    Vol. II, Detonation-Related Detailed Tasks, January, 1973(PDF Vol. II). Two telephone lines will be extended from theirexisting RB-E-01 location to the RB-AR-2 site. These lineswill be at the following locations:Telephone No. 1 EIC (access control trailer)Telephone No. 2 Rig (tool pushers trailer)

    2. RadiosOne radio net will be available to all of the project participants. A base station located at the RB-E-01 and a mobile unitin a CONOCO vehicle will be available for use by AEC/LLL, EIC,and CONOCO/CER personnel. The radio system will connect theRB-AR-2/RB-E-01 sites to the CONOCO Grand Junction office. Thefrequencies of the radio net will be 153.350 MHZ for repeattransmit and 158.370 MHZ for repeat receive. These frequenciescorrespond to Net 2, as described in the PDP Vol. II.

    VehiclesProject participants will be responsible for providing and maintaining their own vehicles.General Operational and Logistics SupportREECo will provide the following general logistical and operational support:1. Miscellaneous Buckslip Items.2. Crafts.3. Clerical (if necessary).4. Drayage.5. Sanitary Facilities.Occupational Health and Safety1. General

    All operations and activities will be conducted in accordancewith the standards of the Occupational Safety and Health Act of1970 (OSHA).

    7

  • 8/7/2019 Pne Rb 57 Rio Blanco

    16/98

    All participating organizations are responsible for the healthand safety of their own personnel and for conducting allactivities in accordance with procedures that assure:a. A safe and healthful environment for the employees.

    b. Control and minimization of hazards to the public and topersonnel of other participants.c. Minimization of the accidental damage or loss of equipment,

    materials, and property.2. First Aid

    REECo will provide each participating agency contacts withlocal medical facilities and physicians in the Grand Junction,Rifle, and' feeker areas for use in the event of accident orillness. Emergency transportation of injured persons of allagencies to a medical facility will be provided.REECo will arrange for and provide first aid supplies asapproved by a physician.

    3. Fire ProtectionHand-operated fire extinguishers will be provided at the welllocations at points convenient to each signficant structure orpiece of equipment. Extinguisher types will be varied forcontrol of Class A, B , or C fi res, as appropriate.

    4. SanitationREECo will provide potable water for drinking and cooking.Chemical or standard toilets will be provided and serviced asrequired. Solid wastes will be disposed of in accordance withlocal regulations.A limited number of trailers at the RB-E-01 well location willbe connected to a nonpotable water source and sewage systeminvolving a septic tank. This will be in accordance with RioBlanco County Planning Directive.

    8

  • 8/7/2019 Pne Rb 57 Rio Blanco

    17/98

    III. REENTRY OPERATIONS

    Drilling Operations1. Phase IHole Characteristics and Drilling Plan-Vertical Hole

    (0-2,200 feet)A 30-inch hole will be drilled to a depth of approximately 20feet and 24-inch OD conductor pipe will be set and cemented tothe surface.A 22-inch hole will be drilled to a depth of 150 feet and surfacecasing (16-inch OD) will be run to a 150-foot depth and cementedto the surface. A 15-inch hole will then be drilled from 150feet to approximately 2,200 feet total depth (TD). The intermediate casing (10 3/4-inch OD) will be run to 2,200 feet andcemented back to surface. A pressure test will be performedon the intermediate casing and wellhead.

    2. Estimated Formation TopsAll drilling, casing and any other depth measurements will be referenced to the kelly bushing. Logging and formation tops will bereferenced to ground level.

    FormationAlluviumGreen River

    Parachute Creek MemberMahogany MarkerBlack MarkerOrange MarkerPiceance Creek SandWasatchFort Union SandMesaverdeTDDrilling Procedure

    Top inTrue VerticalDepth (ft)Surface125

    1257809102,1302,2802,8305,4606,090about 6,250

    Elevation fromMean Sea Level (ft)+ 6,622+ 6,497+ 6,497+ 5,842+ 5,712-1-4,492+ 4,342+ 3,792+ 1,162+ 532+ 372

    a. Use dry hole digger to drill hole for 24-inch conductorpipe. Cement conductor pipe from 20 feet TD to surface.

    b. Build wooden cellar, 8 feet wide, 12 feet long, and 9 feetdeep. Line with steel.

    c. Move in drilling rig and rig up. Concurrently install theContaminated Water Containment System (see Section V ) . This

    9

  • 8/7/2019 Pne Rb 57 Rio Blanco

    18/98

    s y s t e m w i l l b e s i m i l a r t o t h e o n e u s e d f o r RB - E -0 1 r e e n t r y ,a nd i t s i n s t a l l a t i o n w i l l h a v e t h e c o n c u r r e n c e of t h e LLLO p e r a t i o n s D i r e c t o r .D r i l l 1 2 1/4-inch h o l e t o 1 50 f e e t , o p e n 1 2 1/4-inch h o l et o 2 2 i n c h e s .R un 150 f e e t o f 16 - i n ch H - 40 c a s i n g , gu i de shoe on bo t t oma nd b a f f l e c o l l a r o n e j o i n t u p f ro m b o t t o m . Ce me nt t o s u r f a c e . Wa it on cem ent (WOC) 18 h o u r s . Use sl u r r y A (RFCc e m e n t ) , s e e T a b l e I I I - A - 1 .I n s t a l l 1 6 - i n c h c a s i n g h e a d , 1 6 - i n c h h y d r a u l i c BOP, a nd1 6 - i n c h H y d r i l BOP o r d o u b l e g a t e BOP. I n s t a l l k i l l l i n ea n d f l o w l i n e .P r e s s u r e t e s t BOPs a nd c a s i n g w i t h 4 0 0 - p s i g s u r f a c e p r e s s u r e .D r i l l p l u g , c e m e n t , s h o e , an d f o r m a t i o n w i t h 1 5 - i n c h b i t . U sea c e n t r a l i z e d a nd s t a b i l i z e d a ss e m bl y f o r d r i l l i n g t h e 1 5 -i n c h h o l e .D r i l l t h e 1 5 - i n c h h o l e t o 2 , 2 0 0 f e e t . O b t a i n d e v i a t i o ns u r v e y e v e r y t r i p o r a t l e a s t e v e r y 5 0 0 f e e t .Run i n t e g r a t e d c a l i p e r s u r v e y f ro m 2 , 2 0 0 f e e t t o 1 50 f e e tf o r c e m e n t i n g p u r p o s e s .R un 1 0 3 / 4 - i n c h c a s i n g t o 2 , 2 0 0 f e e t w i t h f l o a t s h o e , f l o a t ;c o l l a r , an d s t a g e c o l l a r . Use c e n t r a l i z e r s t h ro u g h o u t t h es t r i n g . I n s t a l l s l i p s i n h e ad b e f o r e c e m e n t in g . (T en j o i n t sof t h e 10 3 / 4 - i n c h c a s i n g t o b e s a n d b l a s t e d . )C em en t f i r s t s t a g e . Us e s l u r r y B ( s e e T a b l e I I I - A - 1 ) . Bumpp l u g o n f l o a t c o l l a r . T e s t t h a t f l o a t e q u ip m e n t i s h o l d i n gp r o p e r l y . D ro p s t a g e c o l l a r o p e n in g b om b . O pen s t a g e c o l l a r ,a nd c i r c u l a t e o u t c em e n t a b o v e t o o l . W a i t 1 2 h o u r s f o r c e m e n tt o s e t . C em en t s e c o n d s t a g e t o s u r f a c e u s i n g s l u r r y C ( s e eT a b l e I I I - A - 1 ) .U nb o l t f l a ng e on 16 - i n ch ca s i n g hea d . R em ove BOPs and c u to f f 10 3 / 4 - i n c h c a s i n g .I n s t a l l 1 6 - i n c h x 1 0 - i n c h S e r i e s 15 00 w e l l h e a d an d t e s tc o n n e c t i o n .I n s t a l l 1 0 - i n c h S e r i e s 9 0 0 o r 15 0 0 d o u b l e g a t e BOP w i t h b l i n dand p i pe ram s and 10 - i n ch S e r i e s 900 o r 1500 H yd r i l and t e s tt o 3 0 0 0 p s i .D r i l l o u t s t a g e c o l l a r a nd c l e a n o u t t o t o p o f f l o a t c o l l a r( a p p r o x i m a t e ly 2 ,1 7 0 f e e t ) .

    10

  • 8/7/2019 Pne Rb 57 Rio Blanco

    19/98

    TABLE I I I - A ^

    SlurryA

    B

    C

    PurposeSurface casing150' to surface22" hole16"casingIntermediatecasing, 1ststage 2,200'to ~1,200'

    Intermediatecasing, 2ndstage

    CEMENT

    Sys temClass G10% D-532% CaCl2

    Class G20% silicasand, retarderas necessary12% gel, 114%H^OClass G20% silicasand, 12%Gel, 114% H O

    SYSTEMS

    Yieldft^/sack1.6

    2.39

    2.39

    AND VOLUMES

    Densitylbs/gal14.2

    13.0

    13.0

    REQUIRED

    Volume Req'dIncl. Excessft3373

    Will be basedon caliper survey

    Will be basedon caliper survey

    PumpingTimeHrs:Min3:10

  • 8/7/2019 Pne Rb 57 Rio Blanco

    20/98

    q. Pr es su re -t es t sta ge co ll ar and 10 3/4- inc h casing with 500-psig surface pre ssur e.

    r. Run cement bond log (CBL) from surface to 2,200 feet. Rungyroscopic direction survey with 50-foot stations fromsurface to TD, both going in and coming out of the hole.

    Surface Equipment and Servicesa. Wellhead

    The starting head 16-inch x 10 3/4-inch will be Series 900.The remaining wellhead will be Series 1500 (5,000-psi working pressure, 10,000-psi test pressure).

    b. Blowout Preventer (BOP) EquipmentA 16-inch hydraulic double-gate Series 900 BOP or a singlegate BOP with a 16-inch Hydril will be used on the well.Series 600 BOPs are acceptable if an adapter flange for theSeries 900 wellhead flange is provided.

    Downhole Equipment and Servicesa. Surface Casing

    Al l ca si ng and downhole equipment w i l l be measured on t herack befor e runn ing in the h ol e. S ix tee n- in ch OD, H-40,65- lb /f t c asin g wi l l be se t at 150 fe et . Thread-loc kingcompound wi l l be used on th e guide shoe and the ba f f leco ll ar lo cat ed one j oi n t above the shoe.

    b. Intermediate CasingThe intermediate casing will consist of 10 3/4-inch OD,Range 3 casing as listed below:

    ID (in.)Depth (ft) Lb/ft Grade Joint Actual DriftSurface to 45.5 P-110 Buttress 9.950 9.7942,200 feet

    c. Centralizers(1) Surface Casing

    A centralizer will be placed approximately 20 feet abovethe guide shoe and then on every collar to the surface.

    (2) Intermediate CasingCentralizers wil l be placed at approximately 15 feet abovethe shoe and on every third casing collar to surface.

    12

  • 8/7/2019 Pne Rb 57 Rio Blanco

    21/98

    Float and Guide Equipment(1) Surface Casing

    A guide shoe will be installed on the bottom join t,and a baffle collar will be located approximately 30feet (one joint) above the guide shoe.

    (2) Intermediate CasingA float shoe will be installed on the bottom jo int,and a float collar will be located approximately 45feet (one joint) above the shoe. A stage cementingcollar will b e positioned in the 10 3/4-inch stringbased on drilling conditions and hole caliper log.

    Drilling FluidFrom surface to 2,200 feet , mud density wil l be held at 9.0to 9.5 lb/gal with viscosity below 50 sec/qt. Viscosity willbe raised as hole conditions dictat e. Drilling fluid waterloss will be maintained at approximately 10 ml AP I. A de -sander and shale shaker will be used to reduce solids in thesystem. Ge l, bar ites , and lost circulation material will beadded as the situation requir es. A daily sample of drillingfluid will be obtained and stored at the site.Drill CuttingsSample cuttings at 30-foot intervals will be obtained fromthe surface to TD. The samples will be washed in wate r,placed in conventional sample bags, and stored at the rigduring the drilling o peration. (When radiological controlsare instituted, this will b e done in the manner prescribedby EIC.)CoresNone planned.D r i l l S t e m T e s t sNone planned.Logging ProgramAll logging depths will be relative to ground level(6,622.5 feet).(1) 15-Inch Ope n Hole

    Integrated Caliper Survey Surface to 2,200 feet(capable of recording up toa 36-inch diameter, minimumof 3 arms)

    13

  • 8/7/2019 Pne Rb 57 Rio Blanco

    22/98

    (2) 10 3/4-Inch Cased HoleCement Bond Log Surface to 2,200 feetGyroscopic Directional Survey Surface to 2,200 feet(with 50-foot stations, inand out with maximum variance

    of 10 feet)j. Deviation Control

    Stabilizers will be used, if necessary, while drilling 15-inch hole.Cementing OperationsThe physical properties and volume required for the cementsystems to be used on the well are given in Table III-A-1. SomeiDodification to cement systems will be made, if required, toachieve desired properties of a specific cement batch.a. Surface Casing

    The voliome for cementing the surface casing includes 100percent excess to ensure circulating cement back to thesurface.b. Intermediate Casing

    (1) First StageThe 10 3/4-inch casing will be cemented in two stages.Mud flush will be pumped ahead of the first stage todisplace the mud. The stage collar at about 1,200 feetwill be opened and any cement above the collar circulated out.

    (2) Second StageAfter waiting 12 hours for cement to set, the upperportion of the 10 3/4-inch casing will be cemented tothe surface through the stage collar.

    c. TestingThickening time and compressive strength tests will be runon samples of the cement to be used just prior to the actualcementing operation.

    Phase IIHole Characteristic and Drilling PlanDirectionalHole (below 2.200 feet)A 9 7/8-inch hole will be drilled, near vertical, to a depth ofapproximately 4,700 feet and then be directionally controlled

    14

  • 8/7/2019 Pne Rb 57 Rio Blanco

    23/98

    toward the middle chimney region of the RB-E-01 well. The MD(measured depth) of the 9 7/8-inch hole will be approximately6,400 feet. Logging will be accomplished (see logging program),if possible, prior to running 7-inch casing in the hole. Afterthe 7-inch casing is cemented, the 10-inch Series 900 or 1500blowout preventer stack will be removed and the 6-inch Series1500 tubing head added to the wellhead. Six-inch Series 1500blowout and snubbing preventers will be utilized until the wellis completed. A balanced drilling fluid column system will beused for drilling or coring from 6,400 feet MD to approximately6,800 feet MD, the interval where it is expected the lost circulation zones will be encountered. The balanced system shouldhelp reduce the loss of fluid into the fractures and cavityregions. A drilling well control (DWC) unit will be used toseparate gas from the mud system.Hole size from approximately 6,400 feet to approximately 6,800feet will be 6 1/4-inches. After reaching total depth (TD), a5-inch flush joint liner will be run into the hole and hungin the 7-inch casing. No cement will be placed behind the liner.Logging will be accomplished and then 2 7/8-inch tubing willbe run to near the top of the 5-inch liner hanger. Plugs willbe used in the 2 7/8-inch tubing as a safety precaution foradditional control of the well. After the tubing hanger islanded in the tubing head with downhole plugs installed inthe tubing, the 6-inch blowout preventer stack will be removedand the remainder of the wellhead will be installed and tested.Two master valves will be used on the tubing head. Plugs willbe pulled by wireline through a lubricator under nitrogenpressure. After the plugs are pulled, the 5-inch flush jointliner will be perforated using a through-tubing perforatinggun.A short-term flow test will be run through the DWC prior toreleasing rig to confirm communication with the second chimney.

    8. Drilling Procedure Below 10 3/4-Inch Casing Deptha. Drill out float collar, stage collar, and formation using

    9 7/8-inch bit.b. Drill vertical 9 7/8-inch hole. Survey at about 4,500 feet.c. Drill 9 7/8-inch hole to kickout point of approximately

    4,700 feet.d. Directionally control 9 7/8-inch hole to approximately

    6,400 feet MD or approximately 6,020 feet true verticaldepth (TVD). Final drilling angle will be approximately60 from the vertical. Directional surveys (utilizing eyetool or similar system) will be run as required. (Exact

    15

  • 8/7/2019 Pne Rb 57 Rio Blanco

    24/98

    true vertical depths and measured depths of 7-inch casingpoint will depend on directional hole and will be recalculated for actual conditions. The depths given here are onlyapproximations).e. Run open hole logs, if possible. (See logging program.)f. Run 7-inch casing and cement first stage. Use slurry A(see Table III-A-2). Open stage collar and circulate. WOCapproximately 18 hours. Set slips and pull 100,000 poundsoyer 7-inch casing weight. Cement second stage to surfaceand WOC, using slurry B (see Table III-A-2).g. Cut off 7-inch casing above slips. Remove 10-inch BOP equipment.h. Install 10-inch x 6-inch Series 1500 tubing head and pressure test.

    9. Drilling Procedure Below 7-Inch Casing Deptha. Install drilling stack and pressure test individual components to 3,000 psi. Ensure that BOP controls on rig floorand remote control functions correctly.b. Pressure test the 7-inch casing to 3,000 psi.c. Install and hook up the DWC unit. The DWC unit representativewill demonstrate the correct functioning and operation ofthe unit. Check out operation of snubbing BOPs and relatedhydraulic valves.d. Test operation of flareline, stack, and purge system usinggas from Fawn Creek Government Number 1 Well.e. Ensure correct operation of recording instruments and alarmsrelated to the drilling liquids systems after pits are atworking levels.f. Check functioning of explosimeter system to ensure theircorrect operation and that alarms are working.g. Ensure that all personnel, equipment, spare parts, andequipment related to reentry are on location and ready.h. Run a 6 1/4-inch bit for drilling and 5-inch drill collarswith a float and a plug receiving nipple immediately abovethe float. Drill pipe and drill collars should be magnafluxinspected prior to the start of the operation.i. Drill stage collar using water.

    16

  • 8/7/2019 Pne Rb 57 Rio Blanco

    25/98

    TABLE III-A-2

    SlurryA

    B

    PurposeCementing from7" casing shoeto the stagecollarCement from7" stud collarto the surface

    CEMENT SYSTEMS

    Sys temClass G, 35%silica sand.10% salt, andretarderClass G, 35%silica sand.10% salt

    Yieldft^/sack1.55

    1.55

    AND VOLUMES

    Densitylbs/gal15.8

    15.8

    REQUIRED

    Volume Req'dIncl. Excessft3Will be basedon caliper survey

    Will be basedon caliper survey

    *To be determined.

  • 8/7/2019 Pne Rb 57 Rio Blanco

    26/98

    j. Mix 400 bbls minimum visbestos mud for standby system. Ifbalance-water system will not contain formation gas owingto excessive lost circulation, the visbestos mud will beused to maintain control of the well. Run directional survey of hole before drilling out of shoe.k. Drill out shoe joint and approximately 100 feet of formation.If partial lost circulation occurs prior to this point, spotpill of mud with lost circulation material (LCM) and trip fornew 6 1/4-inch bit. Run deviation survey prior to pulling outof hole. This step and all subsequent steps will be modifiedif a coring program is agreed upon.1. Run in hole with sidewall sampling tool and new bit.m. Drill ahead until decision is made to stop drilling and/orentry into chimney is achieved, and run liner.n. Run high-intensity gamma ray log through drill string. Obtain sidewall samples as required.o. Run wireline plug into drill pipe and set in plug receivingnipple. Pull out of hole keeping fluid column balanced, ifpossible. Every effort will be made to minimize fluid loss.Snub out of hole, if necessary. (Snubbing equipment and crewwill be on the drill site before drilling out from 7-inchcasing.)p. Run 5-inch flush joint liner and hang liner inside of 7-inchcasing with approximately 50 feet of overlap.q. Run logs. Run temperature survey first to ensure that temper

    ature limits of other logging sondes will not be exceeded.r. Run tubing. Land above liner.s. Nipple up wellhead. Install lubricator.t. Perforate liner and run short production test through DWC

    unit.u. If good communications are established, release rig.

    10. Surface Equipment and Services

    a. WellheadThe wellhead components added for drilling and for finalcompletion for flow testing will be Series 1500 (5,000-psi working pressure, 10,000-psi test pressure).

    18

  • 8/7/2019 Pne Rb 57 Rio Blanco

    27/98

    Figure III-A-1 shows the complete wellhead.Containment EquipmentThe containment equipment or drilling stack employed duringreentry drilling operations is shown on Figure III-A-2. Thestack sits on top of the tubing head during the drilling ofthe 6 1/4-inch hole. All equipment utilized will be Series1500 (5,000-psi working pressure, 10,000-psi test pressure),with the exception of the rotating head which is a rubber-type packoff around the drill pipe and is used to directany small quantities of gas returned with the drilling fluidto the pits during normal drilling operations. Any largerquantities of gas will be diverted through the DWC unit byuse of the Hydril or 3 1/2-inch strippin g ram BOP above thecirculation spool.All individual units of the preventer stack will be shoptested to rated working pressures of 5,000 psi. Field testsof the BOP stack will be conducted to 3,000 psi which exceedsthe expected surface pressure by approximately 500 psi. Because presently available BOP equipment is not capable ofwithstanding a high-temperature environment over extendedperiods, flow testing will not be run through the BOP stack.Field tests will be conducted by installing the blank tubinghanger plug in the wellhead with either 3 1/2-inch internalflush (IF) drill pipe, or 4 3/4-inch CD drill collars, andpressuring above this plug with liquid to test the individual rams of the'BOP equipment. Functional tests of theHydril to 500 psi will also be conducted.Sizes and types of rams have been selected to cover operations in and out of the hole during all of the drillingphases, including snubbing operations during the drillingof the 6 1/4-inch hole.Dual controls for the various BOP units will be used. Oneset will be on the rig floor, and one set will be remotelylocated.Drilling RigThe rig selected will be sized to safely and efficientlyhandle the downhole operations. Substructure height must beat least 17 feet to give clearance for the necessary drilling stack components required for drilling and snubbingoperations. A general layout of the rig is shown in FigureIII-A-3.

    19

  • 8/7/2019 Pne Rb 57 Rio Blanco

    28/98

    LUBRICATOR

    FIG. II I-A -1 RB-AR -2 WELLHEAD STATUS20

  • 8/7/2019 Pne Rb 57 Rio Blanco

    29/98

    Ik00lOCMCM

    ROT.HEAD 6"900 SERIESROTATING HEAD

    CM

    IM

    CM

    CM

    CM

  • 8/7/2019 Pne Rb 57 Rio Blanco

    30/98

    CCESS ROADAccesson trot

    Mud pumpsFAWN CREEK GOV'T t| WELLNO. I- ^ ( S H U T - I Trash

    vFence J_

    XISTINGLOCATION OUTLINE

    Pit IDA^ X

    FIG. I I I - A - 3C O N O C O - U . S. AEC P RO PO SE D WELLLOCATION LAY OUT FOR DRILL ING &CO M P LE TION OF WELL R B- AR - 222

  • 8/7/2019 Pne Rb 57 Rio Blanco

    31/98

    d. Drilling Recording InstrumentsInstruments and recorders will be utilized in conjunctionwith reentry operations to give the following information:(1) Pit volume indicators with alarms to determine changes

    in mud volume.(2) Drilling time, depth, penetration rate, RPM, and hookload will be recorded.(3) Flow sensor on mud return flowline.

    e. Snubbing EquipmentReference PDF, Vol. Ill, Sec. III-2-e, pages 29-32.

    f. Drilling Well Control (DWC)Reference PDF, Vol. Ill, Sec. III-2-f, pages 32-35.

    g. Explosimeter SystemReference PDF, Vol. Ill, Sec. III-2-g, page 35.

    h. Flareline Stack and Purge SystemReference PDF, Vol. Ill, Sec. III-2-h, pages 35-37.

    11. Downhole Equipment and Servicesa. Casing and Tubing

    Casing specifications:(1) 16-Inch Surface Pipe

    Size ODWt./ft.GradeIDDrift IDCollar ODBurst strengthCollapse strengthTensile strengthType connection

    16.00 in.65 lbs./ft.H-4015.250 in.15.062 in.17.00 in.1,640 psi670 psi439,000 lbs.ST&C

    23

  • 8/7/2019 Pne Rb 57 Rio Blanco

    32/98

    (2) 10 3/4-Inch Intermediate StringSize ODWt./ft.GradeIDDrift IDCollar ODBurst strengthCollapse strengthTensile strengthType connection

    (3) 7-Inch Primary CasingSize ODWt./ft.GradeIDDrift IDCollar ODBurst strengthCollapse strengthTensile strengthType connection

    (4) 5-Inch FJ Liner

    10.75 in.45.5 lbs./ft.P-1109.950 in.9.794 in.11.750. in.6,600 psi2,610 psi1,400,000 lbs,Buttress

    7.0 in.23 lb./ft.CYS-956.366 in.6.241 in.7.656 in.7,530 psi4,150 psi636,000 lbs.Buttress

    Size ODWt./ft.GradeIDTensile strengthType connection

    5 in.14.78 lbs./ft.J-554.408 in.228,000 lbs.Atlas Bradford Quadraseal(FL-4S)

    (5) Tubing: 2 7/8-Inch. EUE tubing will be used inside the7-inch casing for an instrument string and for injectingchemicals downhole for corrosion protection of the7-inch casing during flow.Size OD 2.875 in.Wt./ft. with coupling 6.50 lbs.Grade J-55Drift diameter 2.347 in.Coupling OD 3.668 in.Collapse resistance 6,800 psiInternal yield pressure 7,260 psiJoint yield strength 99,660 lbs.

    24

  • 8/7/2019 Pne Rb 57 Rio Blanco

    33/98

    b. Drill Pipe and Drill CollarsContractor-furnished except for 6 1/4-inch hole.The drill string used for reentry below the 7-inch casingwill be 3 1/2-inch IF drill pipe with 18 taper on theshoulders. The pipe will be magnaflux inspected prior torunning in the hole.The drill collars (provided by the AEC) will be approximately4 3/4-inch OD. Special internal bored drill collars areneeded to accommodate the sidewall sampling toolThe drill string will also include a float and plug nipplesabove the float collar to receive retrievable wire-lineplugs run inside of the drill string. The drill collarswill be magnafluxed prior to running into the hole.

    c. Sidewall SamplesThis program will be subject to modification based on thecoring program. However, if no cores are taken, approximately12 sidewall samples may be taken based on the data obtainedduring drilling and from gamma ray logs run through thedrill pipe. If the coring program is implemented, a fewsidewall samples may also be required to supplement thecoring program.

    d. CoringCore samples from the fracture region of the detonationare desired. The project Participants agree to jointlyevaluate, to the best of their ability, possible ways toobtain such core. This evaluation will include possiblecontinuous coring methods and consider costs, risks, andchance of success. Such an evaluation shall have been completed before the 7-inch casing point is reached. If continuous coring is deemed infeasible, obtaining two orthree conventional cores will be evaluated. It is recognized that hole conditions below the 7-inch casing mayshorten or eliminate any attempts at coring.

    e. Downhole Drilling MotorA Dyna Drill will be used for only the directional portionof the hole.

    f. Drilling Fluids(1) A low solids mud system will be used to drill the 9 7/8-inch hole. Mud density will be maintained at approximately

    25

  • 8/7/2019 Pne Rb 57 Rio Blanco

    34/98

    9.0 pounds per gallon. Viscosity will be held toapproximately 40-50 seconds unless hole conditionsindicate higher viscosity is required. Water loss willbe at approximately 10ml API.(2) Water will be used to drill the 6 1/4-inch hole below

    the 7-inch casing point. A balanced system will be usedto prevent the influx of fluids into the wellbore uponthe first indication of loss of returns. Minimum rateswill be utilized to keep water losses to the cavity ata minimum.(3) A visbestos mud system will be mixed and on standbyduring drilling of the 6 1/4-inch hole, if it appearsthat the well cannot be controlled with water only.

    12. Logging Programa. 9 7/8-Inch Open Hole

    1. Dual Induction Laterolog82. Compensated Neutron Porosity3. Compensated Foirmation Density

    Compensated Sonic With VariableDensity Trace

    Logging DepthTD to 5,200'TD to 5,200'TD to 5,200'TD to 5,200'

    b. 7-Inch Cased Hole1. Cement Bond Log2. Gamma Ray Neutron w/Casing Collar Locator3. Directional Survey

    c. 5-Inch Flush Joint Liner1. Temperature Survey2. High-Intensity Gamma Ray3. Gamma-Gamma Density4. Neutron Log

    TD to surfaceTD to 5,200'

    Thru linerThru linerThru linerThru liner

    26

  • 8/7/2019 Pne Rb 57 Rio Blanco

    35/98

    13. Drill Cutting SamplesFrom 2,200 feet to 5,000 feet, single samples every 30 feet willbe sufficient.From 5,000 feet to 7-inch casing point, duplicate cuttingsamples will be required every 10 feet.Below the 7-inch casing point, samples will be obtained everyfive feet or as specified by LLL until such time as circulationis lost. See Chapter V, Radiological Controls.

    27

  • 8/7/2019 Pne Rb 57 Rio Blanco

    36/98

    IV. PRODUCTION TESTING

    GeneralThe production testing will consist of: (1) a flow period to measurethe pressure depletion in the chimney to determine the chimney volumeand effective fracture volume, and (2) a long-term pressure buildupto determine the extent of fracturing and the virgin reservoircharacteristics.Gas samples will be taken during the flow testing and analyzed byLLL to determine the amount and type of radioactive species presentin the produced gas. Compositional analysis will also be run on thesamples to determine the BTU content and chemical composition of thegas being produced. Trace analysis for certain rare gases will beused to determine if communication between the chimneys has beenachieved. Sample containers will be provided by the analyzing agency.

    Site LayoutFigures lV-B-1 and IV-B-2 show the schematic flow diagram of allmajor production test equipment. All of the pressure and temperaturerecorders, the wellhead control equipment, separator, monitors, andliquid storage vessels will be located at the RB-E-01 site. The instrument supply gas, purge gas, and pilot light gas will be suppliedfrom the Fawn Creek Government Number 1 Well.EquipmentThe gas will be produced from the 7-inch casing through the wingvalve to the high-pressure separator. The liquids will be removedat the high-pressure separator and further separated into waterand hydrocarbons. Liquids will then be measured and stored forlater disposal. After passing through the separator, the gas flowrate will be measured at ^ flow prover and the gas burned from theflare stack. If freezing weather conditions are anticipated duringproduction testing, equipment design will include features to prevent water freezing in lines and tanks.1. Wellhead

    Figure IV-C-1 shows the wellhead with the wireline lubricator andcontrol head. The ESDV-1 valve shown in the drawing is the emergency shutdown valve and will be activated by any one of severalcritical conditions. These are listed in Section IV-E.2. Fin Fan Coolers

    Three fin fan coolers are hooked up in parallel to cool theincoming gas stream in order to separate more efficiently theproduced water from the gas stream and to reduce the temperature

    28

  • 8/7/2019 Pne Rb 57 Rio Blanco

    37/98

    ^

    ooIDoexex T O F L A R E S T A C K

    To water disposa l welor f lare stack

    FIG. I V - B - 2PROJECT RIO BLANCOLIQUID STORAGE &DISPOSAL SYSTEMS

  • 8/7/2019 Pne Rb 57 Rio Blanco

    39/98

    STEPS ^ 7:

    WIRELINE SHEAVE

    WIRELINE CONTROL HEAD

    2 7s" TUBING LUBRICATOR

    Yt BLEED VALVE

    WIRELINE TO HOISTWIRELINE BOP'/2 VALVE FOR BLEED OFF a PRESSURE RECORDER

    THERMOWELL E S D V - I4 FLOWLINEmmmmummis' :gp OSEPARATOR2 7 /8 "MASTER i CELLAR1

    FIG. IV -C -1 RB -AR-2 WELLHEAD &LUBRICATOR FOR PRODUCTION TESTING31

  • 8/7/2019 Pne Rb 57 Rio Blanco

    40/98

    of the fluid stream. The total calculated cooling capacity of thethree coolers is 10 million BTUs/hour.SeparatorReference PDP, Vol. Ill, Section IV-C-2, page 55.Flow Rate ProverDownstream of the manual choke will be a short section of linecontaining sampling ports for the chemical and radiochemicalmonitoring. The gas flow rate will be measured using critical-flow provers. When the flow rate reaches sonic velocity throughthe prover, it becomes independent of downstream pressure. Constant rate can be maintained by controlling the upstream pressure. Therefore, corrections for changes in temperature and gasgravity will be made in the upstream pressure to keep the rateconstant.Flare StackDuring the flow test, the gas produced from the chimney will bemeasured and then burned. The hydrocarbon condensate will be injected into the flare stream and burned with the gas.Storage Vesselsa. Water Storage

    The produced water will be stored in the four 400-bbll tanks.The tanks will be piped in parallel with a common overflowconnection at the top. Produced water will be sampled forradioactivity before disposal.b. Condensate Storage

    Two 1,000-gallon, low-pressure storage vessels will be usedto store the condensate until disposal. The tanks are 125-psi working-pressure vessels with a common overflow connection between them. Produced condensate will be sampled forradioactivity before disposal.InstrumentationThe wellhead flowing pressure and temperature and static tubingpressure will be recorded. The upstream and downstream pressuresat the flow prover, flowing temperatures, and gas gravity willalso be measured and recorded. The bottom-hole pressure andtemperature will be measured using Amerada downhole instrumentsduring the first two weeks of the shut-in pressure buildupperiod. After the first two weeks, the bottom-hole pressurewill be recorded using a Sperry Sun surface recording instrument.

    32

  • 8/7/2019 Pne Rb 57 Rio Blanco

    41/98

    Amerada downhole instruments will replace the Sperry Sun thelast week of shut-in pressure buildup. The instruments will becalibrated prior to installation and at the conclusion of testing unless more frequent calibrations are needed.D. Test Schedule

    1. Flow Rate and DurationThe test schedule is designed for one flow period followed by along-term buildup. The test design is for a 10- to 15-day flowperiod at a constant rate of about 8 to 10 MMSCFD. The production test may be shortened or lengthened if the bottom-holepressure response indicates that some modification is required.If the pressure response is close to the expected pressure behavior, the 10- to 15-day flow period should be sufficient. A25 to 40 percent pressure reduction of the initial chimneypressure is desired.

    2. BuildupIt is anticipated that a 60- to 90-day buildup period will berequired.

    3. Data ReportingA daily summary report similar to the one made during January-February testing on RB-E-01 will be used to provide informationto the project participants on a daily basis.

    E. Automation and Alarm SystemsThe test equipment will be equipped with safety features wired toa remote indicating panel located in the alarm and control buildingto ensure adequate control and monitoring of the operation. Thesefeatures are separated into two classes: those to shut down theoperation, and those which require local corrective action. All ofthe functions requiring a shutdown actuate the high/low-pressurevalve located at the wellhead and the secondary shut-in valve atthe separator. Table IV-E-1 outlines the alarm features and thefunctions that each system will actuate.1. Flare Stack Pilot Ignition System

    The pilot lights will be ignited using an electrical arcingsystem. If the pilot lights go out and cannot be reignited, awarning light will be energized on the alarm and control panel.2. Storage Tanks

    The tanks will be equipped with high-liquid-level warning lightindicators (HL-1 through HL-6) to show when a tank is almost

    33

  • 8/7/2019 Pne Rb 57 Rio Blanco

    42/98

    TABLE IV-E-1. OUTLINE OF ALARM AND CONTROL FUNCTIONS.Alarm Function System Activated

    1>QtoWCM1>QCO

    .H1UXCNJ1ug

    (U-uHi-JH

  • 8/7/2019 Pne Rb 57 Rio Blanco

    43/98

    full and flow should be changed to another tank. Both thehydrocarbon and water tanks will have a high-liquid-levelswitch. This float switch will be located above the overflowconnect line between tanks. If, for any reason, the tanks fillto the level of the float switch, indicating all the tanks arefull, the switch (HLL-1 or HLL-2) will actuate an alarm on thecontrol panel and also shut in the test to prevent spilling.Low-liquid-level pump shutdown switches (LL-1 through LL-6)will be Installed on all tanks to prevent operation of thedisposal pump when the tank is empty. This switch will alsolight an alarm on the control panel.SeparatorThe separator will be equipped with three alarm and shutdownfeatures (Figure IV-E-1).a. A flow switch (FS-1) on the pressure relief line will shutthe well in and signal the alarm panel if the rupture disc

    should "pop" and flow is bypassing the separator.b. A high-pressure switch (H/LP-2) will also shut in the welland signal the alarm panel if the downstream flow should beshut off due to freeze up or if the choke valve downstreamof the separator is closed during the flow testing.c. The lowT-pressure switch (H/LP-2) will also shut in the welland signal the alarm panel if a line in the system ruptures.WellheadA high-/low-pressure switch (H/LP-1) will be located on the wellhead tq shut in the well automatically if the pressures shouldexceed the preset limits. The preset limits will be based on theoperating conditions during flow. The lower limit will be set toshut in the well in the event of a line rupture downstream. Ahigh-pressure shut-in seems remote, but if for some reason thewellhead pressure should build above the preset limits, the wellwill shut in to protect the lines downstream from being overpres-sured. The upper limit will be set at or below the rated workingpressure of the wellhead equipment and flow line to the separator.Water Disposal PumpA high-/low-pressure switch (H/LP-3) will be located at the waterdisposal pump (see Figure IV-E-1). If the pressures should exceedthe preset limits, the injection pump will be shutdown and asignal sent to the alarm and control panel. This high-pressurelimit switch protects the wellhead and downhole equipment frombeing over-pressured should the pressure limit switch at the

    35

  • 8/7/2019 Pne Rb 57 Rio Blanco

    44/98

    WATER STORAGE TANKSCONDENSATE

    STORAGE TANKS

    HU.-2

    - ;

    HLL-2FLARE STACK

    M C - i n - f P U M M

    HL-i =srL-I4 0 0BBLTANK

    LL- l

    H/LP-3.ZP !HLL-11

    .__1JH/LP-2r r - -2SOV-21 *

    Fs-.rr;^^:;^

    TYPICAL CONDENSATESTORAGE TANK

    r _ _ _ ^ -I

    TYPICAL WATERSTORAGE TANK

    I /I /I //ESOV-I

    fflSEPARATOR L. -IL.LJ b'- -e^I Z" l ALARM- - _ _ _ T ^ ___ CONTROLPANEL

    rT I !

    i ' "HL-nH/LP-ij RB-AR-2 WELLHEAD j

    iIH/LP-4FAWN CREEKGOVERNMENT NUMBER IWELLHEAD REMOTESHUTDOWNSWITCH-NOT TO SCAte-

    FIG. IV-E-1 SCHEMATIC OF THE S H U T D O W N & ALARM SYSTEM.

  • 8/7/2019 Pne Rb 57 Rio Blanco

    45/98

    pump fail. The low-pressure limit switch shuts down the pumpin the event of pipe failure in the water disposal line from theinjection pump.6. Alarm and Control Panel

    The Alarm and Control Panel will be located in the controlbuilding and will indicate the status of all operating equipment. A timer will be installed that will bypass the automaticshut-in features for a short time during startup.7. Emergency Shutdown Valve

    The emergency shutdown valve (ESDV-1) is the main control function for shutting in the well automatically. The ESDV-1 islocated immediately downstream of the wing valve on the welli-head and is a fail-closed valve held open by pneumatic pressure.SDV-2 will also shut down the flow to the separator and will beactivated at the same time ESDV-1 is activated.A normal override will be installed on the water disposal systemto allow water injection even if the production testing is shutdown.

    F. Water DisposalDuring the flare test period the separated water would be temporarilystored in the four 400-bbl tanks and analyzed for radioactivity.The separated water will be disposed of by one of the followingmethods; however, no order of preference is indicated:

    Vaporized and injected into the flared gasInjection into RB-E-Ol top chimneyInjection into the Fawn Creek Government Number 1 Well as donein previous tests

    G. Recompletion and Testing of Fort Union SandsThe completion of KB-AR-2 to the Ft. Union sand will be done in sucha manner as to allow recompletion of the well back into the middlechimney at some future time. After completion of buildup period onthe middle chimney, the well will be recompleted to determine theflow capacity (kh) of one or more zones opposite the top chimney.The procedure is as follows:1. Remove lubricator and equipment around wellhead.2. Move in workover unit.

    37

  • 8/7/2019 Pne Rb 57 Rio Blanco

    46/98

    3. Install pump in lines on wing valve and tubing.4. Kill well with gelled water or mud.5. Spot cement plug or temporary blocking agent above liner. UseBraden head squeeze.6. Test to see if plug is holding.7. Install tubing plug in tubing.8. Install BOP on tubing head.9. Pull tubing.

    10. Rim bridge plug and set at approximately 6,300 feet.11. Dump bail 2 sacks cement on bridge plug.12. Pressure test bridge plug to 3,000 psi.13. Run gamma ray correlation log and perforate deepest selected zonethat is to be tested. (Number of perforations and frac size to bedesigned after evaluation of the logs.)14. Run tubing and hang above zone.15. Breakdown perforations and perform small frac job.16. Clean up well Immediately. Release rig.17. Shut well in and run pressure instrument just below tubing.18. Establish flow rate and flow test well for two-week period atconstant flow rate, if possible.19. Shut well in for buildup. Estimated time for buildup is a function of the formation kh, but it is anticipated that the buildupwill require at least eight weeks and possibly longer.20. Upon completion of testing and analysis of the data, additionaltesting may be desirable on a second Ft. Union sand to confirmor define testing results of the first zone.21. If a second test is to be run, set bridge plug and complete,

    using steps 13 through 17.

    38

  • 8/7/2019 Pne Rb 57 Rio Blanco

    47/98

    V. RADIOLOGICAL SAFETY AND ENVIRONMENTAL SAMPLING

    A. PurposeThis plan provides guidelines for personnel protection from bothinternal and external radiation to the lowest extent practical.Additionally, it establishes guidelines which will limit contamination to the environment to the lowest levels technically andeconomically feasible. This plan completely replaces all radiological and environmental sampling plans in the Project Rio BlancoDefinition Plan, Volumes I, II, and III, revised January 24, 1973,except as stated in Paragraph V-F.

    B, ScopeThis procedure sets forth the minimum safety criteria for environmental protection, reentry drilling operations into the second RioBlanco cavity, sidewall sampling, coring, and subsequent productiontesting. This will be a phased operation for radiological controlpurposes. The controls are established as a function of drillingdepth. However, in the event that radiation is encountered priorto the stated depth, full radiological coverage will be implemented.1. Rig Up and Drill from the Surface to the Kick-Off Point (KOP)at 4,700 Feet

    All radiation control and monitoring equipment will be set upsimultaneously with rig-up operations. All radiation detectionand effluent monitoring devices will be placed in operationand calibrated prior to start of drilling. Every effort willbe made to ensure that contaminated equipment, if moved fromthe RB-E-01 site to the RB-AR-2 site, is controlled to theextent that all radioactive contamination is contained internally. Radiological surveillance will be provided as required during the movement of this equipment. Once it hasbeen determined that all equipment is functioning properly, astand-down period will be in effect until drilling has reachedthe KOP.Fencing, gates, and trailer arrangements should be configuredat rig up to permit prompt application of radiation exclusionarea controls when contamination is encountered. In general,all trailers should be positioned outside of Radiation ControlledAreas.

    2. Drilling from KOP to 5,600 Feet Total Vertical Depth (TVD)The Radiological Safety Contractor, EIC, shall have minimalpersonnel available to assure that all systems are operationaland to evaluate any alarms. Backshift alarms will be coveredon an on-call basis.

    39

  • 8/7/2019 Pne Rb 57 Rio Blanco

    48/98

    3. Drilling from 5,600 Feet TVD to the 7-Inch Casing Point(at approximately 6,050 Feet TVD)An increased state of readiness will become effective. Theradiological safety contractor will establish mdnimal around-the-clock coverage. All instrumentation will be placed in operation and necessary recalibration will be performed. Spotchecks of drilling chips and mud returns will be made as directed by the Radiological Operations Supervisor (ROS).

    4. Drilling Beyond the 7-Inch Casing Point (at approximately6,050 Feet TVD)Full radiological controls will be implemented. This will include access control, dosimetry, monitoring, sampling, effluent documentation, and contamination control as specified inthis plan.

    5. Production TestingDuring production testing of the second cavity, the gas willbe continuously sampled and monitored for radioactivity content. Radiological controls as specified in Section V-F willbe implemented.

    CriteriaThe criteria for radiological protection and managing contaminatedequipment and soils are specified in Appendix A.Responsibility

    The LLL Operations Director is responsible to the AEC ProjectDirector for the radiological safety of the Rio Blanco AlternateReentry and Production Testing.Representatives from LLL Hazards Control, and the AEC/NV RadiationBranch, will alternate as ROS and report to the on-site LLLOperations Director. The ROS is responsible for the overallradiological coordination with the AEC, CONOCO, LLL, EIC, andother organizations as necessary regarding implementation of thisradiological safety plan.The ROS will maintain liaison with the Colorado State HealthDepartment (CSHD) as appropriate.The EIC shall provide radiological safety support servicesunder contract with CONOCO/CER as directed by the ROS with theconcurrence of the on-site CONOCO/CER representative.

    40

  • 8/7/2019 Pne Rb 57 Rio Blanco

    49/98

    The supervisor of each participating organization will be responsible for assuring that his personnel and associated visitors complywith the requirements of this plan.E. Operational Requirements

    1. Generalized Tasksa. Equipment

    The EIC/CER government-owned trailers will be appropriatelylocated to provide entry control, radiological laboratory,and sample preparation facilities. The basic counting andradiological protection equipment includes:(1) Liquid scintillation and associated sample preparation equipment.(2) Multichannel analyzer.(3) Gross alpha and beta counter.(4) Thermolimilnescent dosimeter (TLD) reader.(5) Portable instriunents are to include alpha, beta,gamma survey instruments, an anemotherm, explosi-meters, toxic gas detection equipment, and moisture analysis gear (i.e., molysieve).(6) Oxidizers.(7) Krypton monitoring chamber.(8) Gas conditioning assembly.(9) Respiratory equipment and supplies.

    (10) Additional monitoring and decontamination equipment as required.

    b. Radiation Controlled AreasA Radiation Controlled Area will be established at theRB-AR-2 site for reentry drilling operations in accordancewith Part VI-B of this plan. The perimeter of the controlled area will be established by the ROS in coordinationwith CONOCO. In general, the controlled area will includethe rig, related drilling equipment, and contaminatedmaterials storage.

    41

  • 8/7/2019 Pne Rb 57 Rio Blanco

    50/98

    c. Personnel Entry/Exit Requirements and RecordsIn order that radiological control can be maintained duringperiods when contamination may be encountered, it is essential that all personnel enter and exit the radiation-controlled area via the EIC access trailer when controls areimposed. These requirements will be modified by the ROS asconditions require.(1) To serve as a control point for personnel or vehicularentry into and exit from the controlled area, theaccess station will be manned on a 24-hour basis whencontrols are placed in effect. The following serviceswill be provided:

    (a) Issuance and collection of TLDs and/or pocketdosimeters for all personnel entering the controlled area.

    (b) Issuance of proper Antl-C clothing (coveralls,gloves, hoods, booties, masks, etc.) as requiredand assuring that appropriate clothing is wornin the prescribed manner.(c) Limited personnel decontamination facilities.(d) Logging of personnel entering and exiting thecontrolled area.(e) Issuance and collection of bioassay kits.(f) Alarm notifications.

    (2) Entry Requirements(a) Appropriate Anti-C gear will be issued and wornas required by the ROS, depending on the natureand level of the radioactive contamination.(b) Signs which list the entry requirements are tobe posted by EIC in conspicuous locations.

    (3) Exit Requirements(a) All personnel will be monitored out through the

    access control trailer and will turn in their TLDand/or pocket dosimeter.

    42

  • 8/7/2019 Pne Rb 57 Rio Blanco

    51/98

    (b) All Anti-C gear will be turned in prior to departing the controlled area. No Anti-C gear will beworn outside of the Radiation Controlled Area.(c) Personnel contamination will be kept as low aspractical. Field decontamination techniques willbe used to reduce skin contamination if required.

    d. Dosimetry and Bioassay Requirements(1) Dosimetry

    (a) A TLD will be worn by all personnel working in theRadiation Controlled Area when controls are imposed.When particulate contamination is encountered,pocket dosimeters will be issued to all personnelworking on the rig.(b) A dosimetry record as specified by AECM 0525 will

    be maintained by the EIC of all persons enteringthe Radiation Controlled Area. TLD badges willbe exchanged monthly, or as necessary, and readout and recorded by the EIC; the monthly reportson all participants will be forwarded to the ROS.A copy will be furnished to each participant'semployer. A composite copy will be provided throughCONOCO/CER to Reynolds Electrical and EngineeringCompany, Inc., Environmental Sciences Department,for incorporation into the NV master dosimetry file.Radiation exposure reporting will be in accordancewith the requirements of AECMs 0525 and 0502.

    (c) Pocket dosimeters will be read when turned in andTLDs will be read and reported to the ROS immediately if pocket dosimeters read in excess of 100mR.(2) Bioassay

    Urine samples will be collected from all project personnel and analyzed for ^H and other analyses deemedappropriate by the ROS before the start of reentrydrilling below the 7-inch casing point, before production testing, and upon an individual's permanentdeparture from the site. Urine samples collected frompersonnel who will routinely work in the RadiationControlled Area will also be analyzed via gammaspectrometry.

    43

  • 8/7/2019 Pne Rb 57 Rio Blanco

    52/98

    (e) Registration of Radioactive SourcesThe EIC will register and maintain a record of each radioactive source having activities greater than the exemptquantities and concentrations listed in Schedules A and Bof 10 CFR 30.70 and 30.71.

    (f) Radioactive Waste DisposalThe following methods of radioactive waste disposal willbe employed (see Appendix A, Part 2 ):(1) Produced tritiated water will be injected into a disposal well or vaporized and injected into the flare.(2) Tritiated hydrocarbon condensates will be disposedof by injection into the flare and burned.(3) Combustible low-level tritiated solid wastes may beincinerated on site if acceptable under appropriateair pollution regulations.

    Soil or other media having levels of tritium in excessof cleanup criteria may be dehydrated on site to reduce the contamination to acceptable levels.Contaminated waste in excess of off-site unrestrictedrelease criteria or contaminated equipment which cannot be decontaminated to release criteria will beappropriately packaged in accordance with DOT regulations and shipped to an approved radioactivity disposal area.

    (g) Equipment and Material DecontaminationAll materials leaving the RB-E-01 pad and the RB-AR-2Radiation Controlled Areas will be Inspected by the EICfor radioactive contamination prior to being removed fromthe site. If necessary, contaminated items will be decontaminated to below the levels given in the AEC radiological safety guidelines (Appendix A ) . The EIC will maintainadequate records of all equipment and material leaving thesite, including description, ownership, monitoring techniques, analytical results, and disposition.If particulate contamination is encountered and the decisionis made to decontaminate on site, an appropriate facilitywill be constructed.

    44

  • 8/7/2019 Pne Rb 57 Rio Blanco

    53/98

    An alternative to developing on-site decontaminationcapability would be to fabricate containers to ship allitems contaminated with particulate radioactivity to theNTS for decontamination. All shipments would be in accordance with DOT regulations and any appropriate securityrequirements.The most economical method for handling particulate-con-taminated materials will depend upon the nature and extentof the contamination, as well as the security and waterdisposal requirements. Since these will not be known inadvance, it is recommended that planning be such as toallow either option to be exercised.

    (h) Radiological Protection ControlIf any radioactivity is detected in excess of levels specified in Items 1 and 2 of the operational guides (AppendixA, Part 2) for a 40-hour workweek, drilling or productiontesting will be shut down in the most expeditious mannerconsistent with safety and good practice in operating theequipment involved. The EIC Supervisor of the radiologicalsafety program shall promptly initiate a comprehensiveradioactivity survey and appropriate cleanup proceduresas directed by the ROS. The LLL Operations Director or AECProject Director, as appropriate, and CONOCO Manager ofOperations together shall determine and institute revisedprocedures to be followed before project work is resimied.

    (i) Radiological Protection DocvmientationThe EIC will provide the ROS and CONOCO daily operationalreports giving the results of all radiation measurementsand sample analyses. Results unexpectedly above backgroundwill be reported immediately. CONOCO will record volijmesof gas and liquids flared or reinjected and CONOCO, throughEIC, will correlate volumetric and specific activity datato docxmient total releases of activity. Final release figures will be developed in conjunction with data suppliedby LLL.

    (j) Constraints on Releases of RadioactivityActual releases of radioactivity to the flare stack willbe compared with conservative upper-limit predictionsappearing in WASH-1519, AEC Final Environmental Statement,Rio Blanco Gas Stimulation Project, April 1972. In theunlikely event that the Integrated actual releases appearto be exceeding the predicted releases in such proportionsof radionuclides as to increase significantly the downwinddose predictions, the production testing schedule will bemodified.

    45

  • 8/7/2019 Pne Rb 57 Rio Blanco

    54/98

    (k) Radiological Safety IndoctrinationA radiological safety indoctrination will be given jointlyby the ROS and EIC to all workers prior to the start ofreentry operations below the KOP and to new workers as theyarrive on site.

    (1) Contaminated Water ContainmentA Contaminated Water Containment (CWC) system will beconstructed at rig up to control waste liquids generatedon the rig or which might develop from leaks in the mudtrain or ancillary rig equipment (e.g., mud tanks, DWC,pipe stand, mud pumps, decontamination facility, etc.).Liquids collected via the CWC system will be sampled inplace or pumped to clean holding containers for samplingand subsequent disposal.

    (m) Radiological and Analytical Procedures ManualThe EIC shall furnish a radiological and analytical proceduresmanual and assure that it is in accordance with this planand its appendices. The analytical procedures shall describein detail all laboratory procedures and techniques to beused, as well as the resulting sensitivities. The manualshall be submitted, through CONOCO/CER, to LLL, HazardControl, and the AEC/NV in adequate time for review andapproval prior to instituting site radiological controls.The manual will be periodically reviewed and updatedto be in accordance with subsequent additions or changesto this plan and appendices.

    (n) Winterizing of EquipmentIf freezing weather conditions are anticipated duringreentry drilling or production testing operations, EICand the LLL Operations Director shall assure that theirequipment is adequately winterized.

    2. Drill Rig Radiological Safety and Controla. Survey and Procedures

    (1) Monitoring personnel will be in continuous attendancewhen controls are imposed.(2) A routine radiological survey of the platform workarea will be performed hourly or more often as required. At the same time, combustible and toxic gassurvey will be made using appropriate equipment. Cellarsurveys shall be made prior to entry, if appropriate.

    46

  • 8/7/2019 Pne Rb 57 Rio Blanco

    55/98

    (3) Pipe breaks will b e monitored as scheduled by the ROSwhen tripping out of the hole and during logging andsurvey operations. In no case will the monitor suspenda radiation detector probe, or any other object, inthe drill pipe.

    (4) The monitor will work as an integral part of thedrill crew to maintain radiation and gas leak surveillance. The monitoring activities must conform to therig work schedule and extreme safety precautions mustalways be exercised when performing activities.

    (5) Samples of the return material (mud, drill cutting,etc.) will be periodically checked for alpha, beta,and gamma radiation in accordance with the scheduleset forth in Appendix B. If the return material isfound to be contaminated, then appropriate steps willbe taken to control, contain, and store the contaminatedmaterial.

    (6) Eating and smoking will not be permitted inside theRadiation Controlled Ar ea. During these times, eatingand smoking will be restricted to designated cleanareas away from the rig. Water or beverage drinking ispermitted on the rig, but after contamination has beenencountered only if disposable cups are used and workgloves are removed. Any exceptions to the above restrictions will require prior approval of the ROS . Largesigns will be posted in the rig area by EIC informingrig personnel of any eating or drinking restrictionsas they become necessary.

    (7) The ROS will be informed at the time radiation levelsgreater than twice background are first detected.This report should include:( a ) R a d i a t i o n r e a d i n g s ( a l p h a , b e t a , an d g an ra ia ).(b) Type of detection instrument.(c) Location where radiation was detected.(d) Drilling depth at the time radiation was detected.

    (e) Time of detection.(8) Any radiation levels significantly greater than back

    ground detected in the work area, which cannot bedefinitely identified as to type, will necessitatethe wearing of full-face masks by all involved pers onnel. A sufficient number of full-face masks will be

    47

  • 8/7/2019 Pne Rb 57 Rio Blanco

    56/98

    kept on the rig at all times for use by personnel asrequired.(9) Cylinders of breathing air with a manifold and hosecapable of a four (4)-mask operation will be on handat the rig. A weekly operational check will be made

    of this equipment by the EIC.(10) The ROS will be informed of all hazardous conditionsthat arise during the reentry drilling operations. Hewill also be informed of any radiation being vented to the atmosphere, including all available Informationas to the quantity and specific nuclides involved.(11) Periodic checks will be made of the drilling mud system(pipes, pumps, tanks, etc.) to detect any uncontainedleakage. If leakage is detected, this should be reportedimmediately to the ROS and CONOCO and repaired by thedrilling contractor.(12) A scheduled swipe program will be set up by the EICfor all work areas and trailers within the RadiationControlled Area, as well as selected locations outsidethe Radiation Controlled Area, to ensure that contamination is not being spread.(13) The EIC will maintain a daily log of significantradiological events during the reentry drilling. Thislog should also include references to important drilling milestones (e.g., loss of fluid, spills, and location, time and date of first activity in various systems, time and date of injections, etc.). A carbon

    copy of this log will be provided to the ROS and CONOCOdaily.(b) Equipment and Instrument Requirements

    (1) A sensitive beta-gamma detector will be provided inthe rig floor work area to sense ^^Kr or other fissionproducts. Continuous recording will be maintained inthe access control trailer. The detector will be setto alarm at twice the normal upper limit of backgroundreadings.(2) A shielded scintillation detector will be installed onthe mud return line and the output continuously recorded in the access control trailer. It will be setto alarm at twice the normal upper limit of backgroundreadings.

    48

  • 8/7/2019 Pne Rb 57 Rio Blanco

    57/98

    (3) EIC personnel will respond to and investigate withportable instruments any alarm and will take appropriate action.

    (4) Area TLD packets will be placed on each c o m e r of therig platform and inside each trailer within the Radiation Controlled Area. The exchange frequency will bedependent on the current radiological conditions.

    (5) A low-volume air sampler will be located in the vicinityof the access control trailer.

    (6) Sufficient 55-gal drums will be on site to store contaminated mud or drill cuttings which may be contaminated above allowable limits.

    (7) The krypton monitoring chamber will be installed tosample the gas from the DWC unit. This system will beon line and fully operational using available gasprior to the initial use of the DWC. The system willbe activated when the DWC unit is used.

    (8) A second shielded scintillation detector wi ll beinstalled on the gas flare line downstream of theDWC, Its output will be continuously recorded in theaccess control trailer. It wil l be set to alarm attwice the normal upper limit of background readings.

    (c) Sample AnalysisThe sample acquisition and frequency of analysis is basedon drilling depth described in the scope (see ChapterVI-A-2). A general discussion of the types of samples andanalyses is set forth below. The sample acquisition schedule is described briefly in Appendix B. A copy of the EIClaboratory analysis forms wil l be provided daily to theROS.(1) Samples of mud will be obtained from the mud return

    line and analyzed for particulate fission productsby gamma spectra at 1 pCi/ml sensitivity referencedto ^^^Cs and by liquid scintillation for ^H at 2pCi/ml sensitivity. [Gamma spectra referred to hereand in subsequent paragraphs will be obtained in thefield with a Nal(Tl)-multichannel system. If nec essary, selected samples can be evaluated by the EICor LLL at their home laboratory wi th a Ge (Li-drifted)detector system.]

    49

  • 8/7/2019 Pne Rb 57 Rio Blanco

    58/98

  • 8/7/2019 Pne Rb 57 Rio Blanco

    59/98

  • 8/7/2019 Pne Rb 57 Rio Blanco

    60/98

    Flow will be continued through the DWC for a period of timeadequate to verify the absence of particulate contaminationin the flow streams.Rig Demobilization and Removal of Equipment from the ControlledAreaa. The decontamination of on-site equipment contaminated withtritium will be performed to achieve surface contaminationlevels no greater than those specified in Appendix A and/orthe guides of AEC Manual Chapter 0524.b. Any items contaminated with particulate radioactivity willbe placed in a holding area for subsequent movement to anauthorized site or for movement to the Nevada Test Sitefor decontamination and return to the owner.c. A log will be maintained by EIC of all items of equipmenton which swipes are taken and analyzed. The log will re

    flect the nomenclature of the equipment, appropriate swipeinformation, and the date that the equipment was releasedfrom the site and disposition.d. Swipes will be taken on all items removed from the Radiation Controlled Area. Any others suspected of being contaminated with radioactivity will also be swiped.Production Testing from Second Chimneya. General

    During production testing of the second chimney, the gasproduced will be continuously sampled and monitored forradioactivity content. This on-line system will be coupledto the gas line downstream from the separator to permitsampling and analysis of the gas to confirm that it iswithin the constraints on releases of radioactivity prescribed in WASH-1519, AEC Final Environmental Statement,Rio Blanco Gas Stimulation Project, April 1972. The requirements of this section shall apply until plugging ofthe well is completed prior to commencing productiontesting from upper intervals. During the buildup period,the requirements will be modified as appropriate to theactivities going on.b. Equipment for Production Test Sampling System

    (See Appendix C for schematic of the production testsampling system.)

    52

    X

  • 8/7/2019 Pne Rb 57 Rio Blanco

    61/98

    c. Site Health PhysicsThe concentration of ^Kr in the flare gas, even assumingminimal atmospheric dilution from the flare stack, isexpected to be well below that which would require personnel dosimetry, that is, one-tenth of the radioactivityconcentration guides found in AEC Manual 0524, Table I.The most likely radiation problem, if one exists, is tritium in the form of separated liquids or water vapor dispersed in the atmosphere. Under these circumstances, thefollowing precautionary and documentary measures will betaken. The possibility exists that particulate activitymay be detected by gas sampling at the gas conditionerassembly filters. If particulate activity is detected,necessary radiological controls will be instituted.(1) Thermoluminescent Dosimeters (TLD)

    TLDs will not be issued to personnel in general.Personnel handling instrument calibration sourceswill be required to wear TLDs. Some area TLDs will beplaced at specific locations about the site; e.g., atthe emplacement well, separator, and flare stack.

    (2) BioassaysAll operating personnel (normally those handling orcontrolling the handling of contaminated material)will submit a urine sample to EIC before the onset ofoperations or upon an individual's arrival on site andpermanent departure from the site. EIC will assay thesamples for tritium and any other analyses deemedappropriate by the ROS.

    (3) SwipesA random swipe program will be conducted by the EICto verify that working, living, and eating areas areradiologically clean. These swipes will be taken atthe beginning of the operation and weekly thereafter.

    (4) Air MoistureA molysieve sample of air moisture, representative ofsite air, will be collected daily and analyzed fortritium by liquid scintillation counting.

    (5) Access ControlAccess to the site will not be controlled, but alog-in, log-out routine will be provided to document

    53

  • 8/7/2019 Pne Rb 57 Rio Blanco

    62/98

  • 8/7/2019 Pne Rb 57 Rio Blanco

    63/98

  • 8/7/2019 Pne Rb 57 Rio Blanco

    64/98

    Daily Effluent ReportThe data obtained from the gas and water analyses will becorrelated with production test and water disposal dataobtained by CONOCO to calculate the daily and cumulativetotal releases of radioactivity to the atmosphere and tothe disposal well. In these calculations, the water vaporcontent of the flared gas will be calculated on the basisof 100 percent saturation at the separator pressure andtemperature conditions, with corrections for gas gravity,if necessary.The effluent report will be prepared dally by CONOCO andEIC and will summarize the releases for the previous 24-hour period ending at 0800. It will be reviewed by theROS.Gas SamplingEIC will collect gas samples (500-cc bottle) and time-correlated liquid samples (25ml minimum) of separatorwater and hydrocarbon condensate (100ml minimum) (ifavailable) for LLL in accordance with the followingschedule:Start-up: One sample after about IMMCF of dry gas flowed.InitialDrawdown: Daily samples or samples at 5MMCF intervals(if high-rate rapid drawdown, daily sampleswill be adequate).ExtendedFlowing: Weekly samples or samples at 5MMCF intervals(whichever is more frequent).Shut-in: One final sample just prior to shut-in.Note: Samples will be spaced to limit to approximately

    15 samples for each test period. All liquid samplesfor off-site tritium analysis will be collected inglass containers.In addition, silica gel/charcoal filter samples of largevolumes of flowing gas will be taken at intervals duringthe test (e.g., weeks 1, 2, 5, and 8 of an eight-week test;or at the start, middle, and end of a short duration test).Gas samples will be taken downstream from the separator,without filtration, to avoid perturbation of the chimneygas composition. Sample bottles must be flushed adequately to eliminate air contamination of the sampled gas.

    56

  • 8/7/2019 Pne Rb 57 Rio Blanco

    65/98

    Flushing should be by flow through the bottle and not byrepetitive filling and venting. If possible, the gas willbe exhausted back into the flare line. Dry gas pressurein a 500-cc bottle must exceed 300 psig to provide anadequate volume of sample for analyses. More than onebottle may be used to obtain sufficient sample if thegas pressure falls below 300 psig.The use of evacuated tanks as a metering reservoir forthe gas passing the silica gel/charcoal filter bedswill be acceptable as long as steam condensation in thetanks is not significant.All samples should be labeled with their date, time,source, pressure, temperature, and such well performancedata (pressure, temperature, flow rate, cumulative flow,etc.) as are available and appropriate to the sample time.Shipment of the samples to LLL will be made within threedays of their collection. These samples will be shippedcollect via motor freight. Any other shipping arrangementswill be the responsibility of the recipient. EIC shallassure that these samples are appropriately packaged ar dshipped in accordance with DOT and AECM 0529 regulations.EIC will also collect samples as requested by outsideagencies, but on a noninterference basis.

    7. Production Testing from Upper IntervalsDuring the drawdown period for each zone tested opposite thetop chimney, the very remote possibility exists that gaseousradioactivity, ^^Kr and ^H, may be produced. Using the ^^Kr asa tracer, the CER Try-Kry will be operated continuously with asensitivity for detection of about 0.02 pCi ^^Kr/cc of gas.EIC will provide adequate personnel and equipment to determinethe radioactivity content of the returned hydrofracture liquids,and to handle the disposal of these liquids in an appropriatemanner as determined by the ROS.If detectable quantities of radioactivity are present in thegas or separated liquids, an evaluation will be made to determine the appropriate radiological controls for subsequenttesting.Prior to conclusion of the production testing of each zone, agrab sample of gas and liquids will be collected and sent toLLL for detailed analyses.

    57

  • 8/7/2019 Pne Rb 57 Rio Blanco

    66/98

    Standby RequirementsWhen operations are to be temporarily interrupted and thesite left unattended except for periodic surveillance, thenthe radiological criteria for site standby in Appendix Ashall be followed. Any equipment or materials remainingon site shall be documented and labeled as to its radiological condition. A status report showing the radiologicalconditions of the site shall be provided to AEC/NV by EICthrough CONOCO. Any subsequent operation not involving CONOCOwill require that the operating organization submit a similarreport to the AEC/NV for approval.Reporting RequirementsThe Technical and Safety Reporting Plan described in ChapterVIII is applicable to the alternate reentry/production-related tasks. In addition to the reports listed in ChapterVIII, the following reports will also be issued:a. EIC Daily Operation Log (EIC)

    Requirements for this report are described in Section V-E.b. EIC Daily Analytical Summary Sheet (EIC)

    This report will be a summary of daily and cumulativeeffluent release data collated from the on-site measurements. (This will also include any Fawn Creek Well gasand liquid radiological data.) It will include bothgaseous release data and liquid disposal data.c. Standby Status Report(s) (EIC/CONOCO)

    This report will include adequate docimientation of thesite radiological conditions at the time of standby (e.g.,known spills and levels involved, flare stack soil levels,waste on hand, and storage location). This report shall besubmitted within 30 days after shutdown.d. Operational Safety, Environmental Protection, and Documentation Report (CONOCO)

    This report shall summarize the daily effluent releases,LLL gas sampling data, and environmental monitoring data.The report is to be submitted in draft within six monthsfollowing completion of the project.

    e. Environmental Monitoring Summary Report (CONOCO)Reports will be submitted to fulfill the requirements ofAECM 0513.

    58

  • 8/7/2019 Pne Rb 57 Rio Blanco

    67/98

    f. Contamination Clearance Report (NV/LLL/CONOCO)This report will be submitted to fulfill the requirementsof AECM 5301. (See Appendix A, Part I, Section III, D.)

    g. AEC Project Director Completion Report for Reentry andProduction Testing (CONOCO/LLL/NV)To include all available data from the completion offlaring to plus 30 days. Inputs are to be received by NVwithin 45 days after completion of flaring.

    h, EIC Raw Data Analytical ReportsCompleted raw data forms from the EIC on-site laboratorywill be submitted to NV on a weekly basis.

    1. LLL Sample Analysis ReportsPreliminary and final reports of analysis of samples sentto LLL shall be submitted to CONOCO, CER, and NV.

    Environmental Sampling Program1. Environmental Sampling Program

    The existing environmental sampling program will be continuedthrough the quarter-year ending July 31, 1974, as stated inthe Operational Safety and Environmental Monitoring for Extended Flaring Program dated January 24, 1974.Review and eva