20
Monitoração do Sistema de Proteção Catódica 1 Friday, June 22, 12

Transcript of Nortech Monitoração da Proteção Catódica

Monitoração do Sistema de Proteção Catódica

1

Friday, June 22, 12

2

Como esta o seu sistema de proteção

CATÓDICA?

Friday, June 22, 12

O sistema de proteção catódica3

Tubo

Friday, June 22, 12

Visitas presenciais

4

‣Mão de obra intensa

‣Equipe treinada pouco aproveitada

‣Tempo de ocorrência do problema

‣Confiabilidade da leitura as vezes questionável

‣SMS (dificuldade de acesso, riscos e impacto ambiental)

‣Alto custo

Friday, June 22, 12

O Sistema MerlinA solução completa para o sistema de monitoração da proteção catódica:

Monitores para retificadores

Monitores para pontos de teste

Sistema supervisório

5

Friday, June 22, 12

Monitoração do Retificador‣Fonte AC

‣Voltagem de saída do retificador

‣Corrente de saída do retificador

‣Potencial on

‣Potencial off

6

Friday, June 22, 12

Recursos‣Verificação horária do retificador

‣Relatório semanal - valores min, max e médio por canal

‣Alarmes enviados dentro de uma hora

‣Controle da saída do retificador

‣Alta reistência a surtos

‣Bateria de 2 anos

7

Friday, June 22, 12

2

Accessory storage trayConveniently store Genny4 accessories, including

the supplied magnet, earth stake and direct

connection leads

High contrast display with auto-backlight Bargraph ‘tidemark’ enables operators to quickly spot

and zero-in on a buried conductor.

High speed USB 2.0 data connectionConnect to a PC to configure C.A.T settings, run

an eCert™, and to rapidly transfer usage data from

eC.A.T4 series locators

Detachable loudspeaker

for use in noisy environments

Sensitivity control

Battery (2 x D-Cell) and USB

data connection compartment

Lightweight high impact ABS casing provides

protection to IP54 for all-weather operation

Replaceable wear boot

Mode selector

switch

Signal boost

button

Accessory

connection socket

Accessory storage tray

Loudspeaker

Battery compartment

(4 x D-Cell)

On/off switch

C.A.T4 Cable Avoidance Tool rangeNext-generation digital design with the classic

Radiodetection C.A.T look and feel.

Genny4 signal generatorLocate more, and smaller, utilities with dual

power and simultaneous dual frequency design.

Depth estimation buttonTrigger switch – intuitively control

power on/off

Recursos avançadosInterrupção sincronizada para passo a passo e DCVG*Gerador para localização do duto**requer MERLIN Interrupter

8

Friday, June 22, 12

Sistema MERLIN com Interruptor

9

Commercial Page 17 of 28 DOC-001-01-017-V31

5.5.4 MERLIN Interrupter or Mercury Relay

As detailed in sections 5.4.2 and 5.4.5, if a MERLIN Interrupter is being installed please refer to the MERLIN Inter-

rupter Installation Instructions, however:

0V (Terminal C) should be connected to MERLIN Interrupter Terminal C

FS (Terminal D) should be connected to MERLIN Interrupter Terminal D

INT (Terminal E) should be connected to MERLIN Interrupter Terminal E

–ve (Terminal K) should be connected to MERLIN Interrupter Terminal K

+ve (Terminal L) should be connected to MERLIN Interrupter Terminal L

If a mercury relay is used, connect the drive connections for the mercury relay to 0V and INT.

See section 7 for installation examples.

5.5.5 Surge Filter

The surge filter is only applicable for a MERLIN Excel with a MERLIN Interrupter installation where the Pipeline Lo-

cate feature is required.

The surge filter is fitted between the rectifier’s positive and negative output as shown below.

See section 7 for more installation examples.

Friday, June 22, 12

Exemplos de instalações

10

Friday, June 22, 12

Monitoração pontos de teste1 Canal - Potencial ON2 Canal - Potencial OFF ou um 2o Potencial ON3 Canal - corrente do coupon

11

Friday, June 22, 12

Recursos‣Checagem diária dos parâmetros da proteção catódica

‣Monitoração CC e CA em todos os canais

‣Relatório semanal - valores min, max e médio por canal

‣Alarmes enviados automaticamente

‣Diagnóstico horário

‣Tamanho compacto

12

Friday, June 22, 12

13

Pontos de difícil acesso

Estradas movimentadas ou com linhas de trens

Pontos intermediários entre retificadores (baixa PC)

Junções entre dutos / juntas de isolação

Dutos próximos ou em paralelo com linhas de transmissão

Possíveis locais de instalação

Friday, June 22, 12

Exemplos de instalações

14

Friday, June 22, 12

ComunicaçãoPor SMS ou Satélite quando não há cobertura GSM

15

Friday, June 22, 12

Ex.dados retificador16

Friday, June 22, 12

Ex.dados ponto de teste17

Friday, June 22, 12

Case Colonial Pipeline

‣4000 km‣382 milhões litros/dia

‣Analisádos 12 equipamentos‣9 testados em campo‣5 para avaliação detalhada

18

‣Integração‣Facilidade de Instalação e Comissionamento

‣Dimensões‣Resiliência‣Comunicação em 2 vias‣Sincronização

Fatos Motivo da escolha pela Abriox

Friday, June 22, 12

Benefícios

19

Aumento da confiabilidade operacional do sistemaRedução de custosRedução de riscos de SMS

Friday, June 22, 12

Contatos

20

www.nortech.com.br

Adriano Camino | Diretor [email protected]

skype: adriano.c.trovato

mobile: +55 11 8100-9050 telefax: +55 21 2493-1098

Av. Dalcídio Jurandir, 255 – sl. 255 – Barra da Tijuca

22631-250 - Rio de Janeiro - RJ – Brasil

Friday, June 22, 12